511 S OCEAN FRONT WALK BUILDING 2 90291
Certificate Information: 511 S OCEAN FRONT WALK BUILDING 2 90291
- Application / Permit
- 23016-10000-24420
- Plan Check / Job No.
- B23LA13533
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- REPLACE FIRE DAMAGED FRAMING MEMBERS FOR UNIT 9 BLDG 2. *NO WORK TO UNIT #7* REROOF BUILDING AND REPLACE ALL DRY WALL AND INSULATION (UNIT 7 WILL BE PROTECTED IN PLACE AND NO REPAIR OR REMODEL WORK WILL BE PERFORMED AT THIS UNIT).
- Permit Issued
- Issued on 10/18/2023
- Issuing Office
- Current Status
- Permit Finaled on 12/2/2024
Permit Application Status History
| Submitted | 7/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/27/2023 | JOE VO |
| Corrections Issued | 7/29/2023 | JOE VO |
| Quality Review Completed | 8/1/2023 | GARO TELMI |
| Plan Check Approved | 10/18/2023 | JOE VO |
| Issued | 10/18/2023 | APPLICANT |
| Permit Finaled | 12/2/2024 | FARHAD DADBIN |
Permit Application Clearance Information
| DAS Clearance | Cleared | 9/5/2023 | Kevin Morales |
| Coastal Zone | Cleared | 9/28/2023 | JASON CHAN |
| Specific Plan | Cleared | 9/28/2023 | LUIS LOPEZ |
| Tenant Habitability Plan | Cleared | 10/4/2023 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | California Premier Builders Llc; Lic. No.: 1032152-B | , |
| Contractor | Premier Restoration; Lic. No.: 1032152-B | , |
| Engineer | Ionescu,, Benjamin; Lic. No.: NA65482 | , |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/25/2023 | Partial Inspection | FARHAD DADBIN |
| Wood Frame | 6/12/2024 | Corrections Issued | FARHAD DADBIN |
| Insulation | 6/17/2024 | Approved | RICARDO ROBLES |
| Drywall Nailing | 6/25/2024 | Approved | FARHAD DADBIN |
| Final | 11/15/2024 | Not Ready for Inspection | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 11/15/2024 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 11/15/2024 | Approved | FARHAD DADBIN |
| Final | 12/2/2024 | Permit Finaled | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 12/2/2024 | SGSOV Approved | FARHAD DADBIN |