3517 S ALSACE AVE 90016
Certificate Information: 3517 S ALSACE AVE 90016
- Application / Permit
- 23016-10000-24035
- Plan Check / Job No.
- B23LA13377
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ALTERATION REPAIR TO (E) SFD, NO SQFT ADDED
- Permit Issued
- Issued on 9/5/2023
- Issuing Office
- San Pedro
- Current Status
- Permit Finaled on 5/3/2024
Permit Application Status History
| Submitted | 7/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2023 | KHUONG TRUONG |
| Corrections Issued | 7/20/2023 | KHUONG TRUONG |
| Issued | 9/5/2023 | APPLICANT |
| Permit Finaled | 5/2/2024 | RICHARD DOCKUS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Arend & Associates Inc; Lic. No.: 685178-B | 101 S BROADWAY UNIT D REDONDO BEACH, CA 90277 |
| Engineer | Nohroodi,, Nader Gholi; Lic. No.: C36971 | 7389 PERIGORD CT TUJUNGA, CA 91042 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/18/2023 | Corrections Issued | JOSE AVILA |
| Deputy Drilled-In Anchors | 10/30/2023 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 11/1/2023 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 11/8/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 11/27/2023 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2023 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 11/27/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 11/27/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Shower Pan | 11/27/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Insulation | 11/30/2023 | Approved | STUART CHAPMAN |
| Drywall Nailing | 12/11/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/11/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Drywall Nailing | 12/15/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Interior/Exterior Lathing | 12/15/2023 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 12/22/2023 | Approved | JOSH MEISTER |
| Final | 4/11/2024 | Not Ready for Inspection | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 4/11/2024 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 4/11/2024 | Corrections Issued | RICHARD DOCKUS |
| Final | 4/18/2024 | Not Ready for Inspection | RICHARD DOCKUS |
| Smoke Detectors | 4/18/2024 | Not Ready for Inspection | RICHARD DOCKUS |
| Pre-Inspection | 4/24/2024 | Corrections Issued | RICHARD DOCKUS |
| Final | 5/2/2024 | Permit Finaled | RICHARD DOCKUS |
| Smoke Detectors | 5/2/2024 | Approved | RICHARD DOCKUS |