1939 N CARMEN AVE 90068
Certificate Information: 1939 N CARMEN AVE 90068
- Application / Permit
- 23016-10000-23798
- Plan Check / Job No.
- B23LA13296
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: -REMODEL AND ADDITION TO EXISITNG 2-STORY SINGLE FAMILY DWELLING. -PROPOSED BREEZEWAY AT REAR OF (E) 2-STORY SFD TO BECOME ATTACHED TO (E) GARAGE
- Permit Issued
- Issued on 11/13/2023
- Issuing Office
- Current Status
- CofO Issued on 3/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/3/2023 | JAD BASMA |
| Corrections Issued | 8/11/2023 | KHEDER ALRAZAA |
| Quality Review Completed | 8/28/2023 | MICHAEL PEREZ |
| Applicant returned to address corrections | 10/19/2023 | JAD BASMA |
| Plan Check Approved | 11/8/2023 | JAD BASMA |
| No Progress | 11/8/2023 | JAD BASMA |
| Plan Check Approved | 11/8/2023 | JAD BASMA |
| Issued | 11/13/2023 | APPLICANT |
| CofO in Progress | 3/7/2025 | CRAIG VAUGHAN |
| Permit Finaled | 3/9/2025 | DEROLD HAUFF |
| CofO Issued | 3/9/2025 | DEROLD HAUFF |
| Permit Finaled | 3/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/7/2023 | ROBERT HUGHES |
| Roof/Waste drainage to street | Cleared | 9/9/2023 | TERRY PHAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2023 | TERRY PHAN |
| Sewer availability | Cleared | 9/11/2023 | TERRY PHAN |
| Low Impact Development (LID) | Cleared | 11/8/2023 | TOMMY YIN |
Contact Information
| Contractor | Wonk Construction Inc; Lic. No.: 1040791-B | , |
| Engineer | Kim,, Hong Kook; Lic. No.: NA64529 | , |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/15/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 12/28/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 12/28/2023 | Corrections Issued | STUART CHAPMAN |
| Pre-Inspection | 12/28/2023 | Partial Inspection | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 2/15/2024 | Approved | STUART CHAPMAN |
| Deputy Wood Construction | 2/15/2024 | Approved | STUART CHAPMAN |
| Deputy Reinf. Concrete | 2/16/2024 | Conditional Approval | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2024 | Corrections Issued | ROY SPAULDING |
| Footing/Foundation/Slab | 2/27/2024 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2024 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 5/8/2024 | Approved | ROY SPAULDING |
| Pre-Inspection | 5/8/2024 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 5/13/2024 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 5/13/2024 | Approved | ROY SPAULDING |
| Green Building Rough | 5/13/2024 | Approved | ROY SPAULDING |
| HVAC-Rough | 5/13/2024 | Corrections Issued | ROY SPAULDING |
| MERV13>=Rough | 5/13/2024 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 5/20/2024 | Corrections Issued | BRIAN SULLIVAN |
| HVAC-Rough | 5/20/2024 | Corrections Issued | BRIAN SULLIVAN |
| HVAC-Rough | 5/22/2024 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 5/30/2024 | Approved | ROY SPAULDING |
| Deputy Steel/Welding | 6/24/2024 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 6/26/2024 | Approved | ROY SPAULDING |
| Insulation | 6/28/2024 | Approved | ROY SPAULDING |
| Drywall Nailing | 7/15/2024 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 7/15/2024 | Partial Approval | ROY SPAULDING |
| Shower Pan | 7/24/2024 | Approved | ROY SPAULDING |
| Pre-Inspection | 11/20/2024 | Partial Approval | CRAIG VAUGHAN |
| Service/Power Release | 11/25/2024 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 2/19/2025 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Final | 2/19/2025 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Final | 2/21/2025 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 2/21/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Final | 2/21/2025 | Approved | CRAIG VAUGHAN |
| Final | 2/27/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Final | 2/27/2025 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 2/27/2025 | Corrections Issued | CRAIG VAUGHAN |
| MERV13>=Final | 2/27/2025 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 2/27/2025 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 2/27/2025 | Approved | CRAIG VAUGHAN |
| Final | 3/6/2025 | OK to Issue CofO | CRAIG VAUGHAN |
| HVAC-Final | 3/6/2025 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 3/6/2025 | SGSOV Approved | CRAIG VAUGHAN |