4524 W YOSEMITE WAY 90065
Certificate Information: 4524 W YOSEMITE WAY 90065
- Application / Permit
- 23016-10000-23680
- Plan Check / Job No.
- B23LA13240
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EXISTING DETACHED CARPORT TO BE CONVERTED TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) "COMPLY WITH DEPARTMENT ORDER effective date 04/07/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". CEIS Case #981819.
- Permit Issued
- Issued on 12/22/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/22/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2023 | ADAM HEGAZI |
| Corrections Issued | 7/22/2023 | ADAM HEGAZI |
| Building Plans Picked Up | 7/26/2023 | APPLICANT |
| Plan Check Approved | 12/20/2023 | GEORGE ALVAREZ |
| Issued | 12/22/2023 | APPLICANT |
| CofO in Progress | 8/12/2025 | DANIEL DELACRUZ |
| Permit Finaled | 1/22/2026 | DANIEL SANCHEZ |
| CofO Issued | 1/22/2026 | DANIEL SANCHEZ |
| Permit Finaled | 1/22/2026 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 11/30/2023 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 12/4/2023 | JUSTIN BICOL |
| Sewer availability | Cleared | 12/5/2023 | JUSTIN BICOL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chang,, Yeh; Lic. No.: S6868 | 168 S SIERRA MADRE BLVD 109 PASADENA, CA 91107 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/24/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Pre-Inspection | 2/2/2024 | Corrections Issued | RAUL VASQUEZ |
| Footing/Foundation/Slab | 6/5/2024 | Partial Approval | DANIEL DELACRUZ |
| Footing/Foundation/Slab | 7/15/2024 | Approved | PEDRO SIERRA |
| BUILDING-Rough-Frame | 9/16/2024 | Partial Inspection | DANIEL DELACRUZ |
| ELECTRICAL-Rough | 9/16/2024 | Partial Approval | DANIEL DELACRUZ |
| Green Building Rough | 9/16/2024 | Approved | DANIEL DELACRUZ |
| HVAC-Rough | 9/16/2024 | Not Ready for Inspection | DANIEL DELACRUZ |
| PLUMBING-Final | 9/16/2024 | Not Ready for Inspection | DANIEL DELACRUZ |
| PLUMBING-Rough | 9/16/2024 | Approved | DANIEL DELACRUZ |
| Sewer | 9/16/2024 | Approved | DANIEL DELACRUZ |
| Underground Mechanical | 9/16/2024 | Approved | DANIEL DELACRUZ |
| BUILDING-Rough-Frame | 9/24/2024 | Approved | DANIEL DELACRUZ |
| ELECTRICAL-Rough | 9/24/2024 | Approved | DANIEL DELACRUZ |
| Insulation | 9/24/2024 | Approved | DANIEL DELACRUZ |
| Drywall Nailing | 10/8/2024 | Approved | PEDRO SIERRA |
| Final | 5/1/2025 | Corrections Issued | DANIEL DELACRUZ |
| SGSOV-Seismic Gas S/O Valve | 5/1/2025 | SGSOV Approved | DANIEL DELACRUZ |
| Smoke Detectors | 5/1/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| ELECTRICAL-Final | 6/26/2025 | Partial Approval | DANIEL DELACRUZ |
| Green Building Final | 6/26/2025 | Approved | DANIEL DELACRUZ |
| HVAC-Final | 6/26/2025 | Approved | DANIEL DELACRUZ |
| PLUMBING-Final | 6/26/2025 | Approved | DANIEL DELACRUZ |
| Smoke Detectors | 6/26/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| ELECTRICAL-Final | 8/11/2025 | Approved | DANIEL DELACRUZ |
| Final | 8/11/2025 | OK to Issue CofO | DANIEL DELACRUZ |
| Smoke Detectors | 8/11/2025 | Approved | DANIEL DELACRUZ |