5710 S CRENSHAW BLVD 90043
Certificate Information: 5710 S CRENSHAW BLVD 90043
- Application / Permit
- 23016-10000-23655
- Plan Check / Job No.
- B23LA05706
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- TRASH ENCLOSURE
- Permit Issued
- Issued on 1/23/2024
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 12/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/30/2023 | HERNAN ARREOLA |
| Corrections Issued | 4/20/2023 | HERNAN ARREOLA |
| Quality Review Completed | 4/20/2023 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 4/21/2023 | APPLICANT |
| Disabled Access Plans Picked Up | 5/26/2023 | APPLICANT |
| Applicant returned to address corrections | 6/29/2023 | HERNAN ARREOLA |
| Applicant returned to address corrections | 12/19/2023 | HERNAN ARREOLA |
| Plan Check Approved | 1/4/2024 | HERNAN ARREOLA |
| Issued | 1/23/2024 | APPLICANT |
| Permit Finaled-Status Void | 9/26/2024 | DARRYL ARNOLD |
| Permit Finaled | 9/26/2024 | DARRYL ARNOLD |
| Re-Activate Permit | 12/3/2024 | DARRYL ARNOLD |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | S P C Industries Inc; Lic. No.: 433163-B | 22212 VENTURA BLVD WOODLAND HILLS, CA 91364 |
| Engineer | Mcdonald,, James Alan; Lic. No.: S4766 | 6 MACAW ALISO VIEJO, CA 92656 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 3/20/2024 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 3/21/2024 | Partial Approval | ALFREDO LOPEZ |
| Masonry Wall/Backfill | 4/1/2024 | Partial Approval | ALFREDO LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2024 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 4/30/2024 | Approved | DARRYL ARNOLD |
| Final | 5/30/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Green Building Final | 5/30/2024 | Conditional Approval | DARRYL ARNOLD |
| Smoke Detectors | 5/30/2024 | Approved | DARRYL ARNOLD |
| Final | 9/26/2024 | Permit Finaled | DARRYL ARNOLD |
| Green Building Final | 9/26/2024 | Approved | DARRYL ARNOLD |