4063 1/2 S SUTRO AVE 90008
Certificate Information: 4063 1/2 S SUTRO AVE 90008
- Application / Permit
- 23016-10000-23506
- Plan Check / Job No.
- B23LA13184
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT (E) 17'2" X 18'1" ATTACHED 2-CAR GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(C). WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 10/23/2023
- Issuing Office
- Current Status
- CofO Corrected on 9/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2023 | MADISON ODELL |
| Corrections Issued | 7/29/2023 | MADISON ODELL |
| Applicant returned to address corrections | 8/21/2023 | MADISON ODELL |
| Applicant returned to address corrections | 8/30/2023 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 9/5/2023 | ARSALAN SHABESTARI |
| Plan Check Approved | 9/6/2023 | ARSALAN SHABESTARI |
| Issued | 10/23/2023 | APPLICANT |
| CofO in Progress | 9/20/2024 | ALFREDO LOPEZ |
| CofO Issued-Status Void | 9/24/2024 | ERNESTO CORRAL |
| Permit Finaled-Status Void | 9/24/2024 | ERNESTO CORRAL |
| Re-Activate Permit | 9/25/2024 | ERNESTO CORRAL |
| Permit Finaled | 9/25/2024 | ERNESTO CORRAL |
| CofO Corrected | 9/25/2024 | ERNESTO CORRAL |
| Permit Finaled | 9/25/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 8/19/2023 | CELINA MORENO |
| Sewer availability | Cleared | 8/19/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2023 | CELINA MORENO |
| Tenant Habitability Plan | Cleared | 8/29/2023 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/8/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 3/20/2024 | Approved | DARRYL ARNOLD |
| Insulation | 3/28/2024 | Partial Approval | ALFREDO LOPEZ |
| Wood Frame | 3/28/2024 | Partial Approval | ALFREDO LOPEZ |
| Interior/Exterior Lathing | 4/4/2024 | Approved | DARRYL ARNOLD |
| Wood Frame | 4/4/2024 | Approved | DARRYL ARNOLD |
| Insulation | 4/8/2024 | Approved | ALFREDO LOPEZ |
| Drywall Nailing | 4/11/2024 | Approved | ALFREDO LOPEZ |
| Interior/Exterior Lathing | 4/11/2024 | Approved | ALFREDO LOPEZ |
| Final | 6/10/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 6/10/2024 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 6/10/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 8/27/2024 | OK to Issue CofO | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 8/27/2024 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 8/27/2024 | Approved | ALFREDO LOPEZ |