5234 N NOBLE AVE 91411

Certificate Information: 5234 N NOBLE AVE 91411

Application / Permit
23016-10000-23147
Plan Check / Job No.
B23LA13029
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan* Convert (E) Storage and Garage into an ADU per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 8/10/2023
Issuing Office
Current Status
CofO Issued on 4/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/14/2023 APPLICANT
Assigned to Plan Check Engineer 7/21/2023 AMY GUEVARRA
Corrections Issued 7/25/2023 AMY GUEVARRA
Applicant returned to address corrections 8/4/2023 JOHNPAUL ISIP
Plan Check Approved 8/10/2023 CAROLEAN BASMA
Issued 8/10/2023 APPLICANT
CofO in Progress 3/6/2024 THOMAS FINNILA
Permit Finaled 4/24/2024 RUBEN SALAS
CofO Issued 4/24/2024 RUBEN SALAS
Permit Finaled 4/24/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/26/2023 RYAN KIM
Eng Process Fee Ord 176,300 Cleared 7/26/2023 RYAN KIM
Sewer availability Cleared 7/26/2023 RYAN KIM

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: NA21514       ,
Contractor Owner-Builder       ,

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/23/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 8/24/2023 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/14/2023 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/18/2023 Partial Approval RYAN SALAZAR
Wood Frame 9/18/2023 Partial Approval RYAN SALAZAR
Sewer 9/20/2023 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 10/13/2023 Not Ready for Inspection THOMAS FINNILA
Gas Test 10/13/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 10/13/2023 Not Ready for Inspection THOMAS FINNILA
Sewer 10/13/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 10/18/2023 Approved THOMAS FINNILA
Sewer 10/18/2023 Approved THOMAS FINNILA
Gas Test 10/20/2023 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 10/20/2023 Approved THOMAS FINNILA
Rough-Elec/Plmb/HVAC 11/2/2023 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 11/7/2023 Not Ready for Inspection THOMAS FINNILA
Rough-Elec/Plmb/HVAC 11/7/2023 Partial Approval THOMAS FINNILA
Deputy Drilled-In Anchors 11/8/2023 Conditional Approval DAVID MATSON
Rough-Elec/Plmb/HVAC 11/9/2023 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 11/14/2023 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 11/14/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 11/16/2023 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 11/17/2023 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 11/17/2023 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 11/21/2023 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 11/22/2023 Partial Approval THOMAS FINNILA
Insulation 11/27/2023 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 11/28/2023 Approved THOMAS FINNILA
Drywall Nailing 12/1/2023 Approved THOMAS FINNILA
Shower Pan 12/15/2023 Not Ready for Inspection THOMAS FINNILA
Deck 12/19/2023 Not Ready for Inspection THOMAS FINNILA
Shower Pan 12/19/2023 Approved THOMAS FINNILA
ELECTRICAL-Final 1/29/2024 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 1/29/2024 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 1/29/2024 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 1/31/2024 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 1/31/2024 Corrections Issued THOMAS FINNILA
HVAC-Final 2/6/2024 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 2/7/2024 Approved CHRISTOPHE COCHRAN
Final 2/7/2024 Corrections Issued CHRISTOPHE COCHRAN
HVAC-Final 2/7/2024 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 2/7/2024 Approved CHRISTOPHE COCHRAN
Final 2/9/2024 No Access for Inspection DAVID MATSON
Green Building Final 2/9/2024 No Access for Inspection DAVID MATSON
SGSOV-Seismic Gas S/O Valve 2/9/2024 No Access for Inspection DAVID MATSON
Smoke Detectors 2/9/2024 No Access for Inspection DAVID MATSON
Final 2/14/2024 Not Ready for Inspection JOHN COLEMAN
Green Building Final 2/14/2024 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 2/14/2024 SGSOV Approved JOHN COLEMAN
Smoke Detectors 2/14/2024 Approved JOHN COLEMAN
Final 3/1/2024 Corrections Issued THOMAS FINNILA
Final 3/5/2024 OK to Issue CofO THOMAS FINNILA