125 N VENDOME ST 90026
Certificate Information: 125 N VENDOME ST 90026
- Application / Permit
- 23016-10000-22983
- Plan Check / Job No.
- B23LA12902
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. Convert (E) DETACHED GARAGE IN THE REAR OF THE LOT TO AN ADU PER CA GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 12/7/2023
- Issuing Office
- Current Status
- CofO Issued on 12/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2023 | ALFREDO JARA |
| Corrections Issued | 7/22/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 9/15/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 10/3/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 10/10/2023 | AMY GUEVARRA |
| Applicant returned to address corrections | 10/27/2023 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 11/16/2023 | AMY GUEVARRA |
| Plan Check Approved | 12/3/2023 | AMY GUEVARRA |
| Issued | 12/7/2023 | APPLICANT |
| CofO in Progress | 12/2/2025 | FREDDIE RIVERA |
| CofO in Progress | 12/2/2025 | DEROLD HAUFF |
| No Progress | 12/2/2025 | DEROLD HAUFF |
| Permit Finaled | 12/18/2025 | DEROLD HAUFF |
| CofO Issued | 12/18/2025 | DEROLD HAUFF |
| Permit Finaled | 12/18/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| ZA Case | Cleared | 8/2/2023 | RYAN LY |
| ZI | Cleared | 8/2/2023 | RYAN LY |
| Address approval | Cleared | 8/5/2023 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 8/5/2023 | CHRISTINA BRACO |
| Sewer availability | Cleared | 8/5/2023 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2023 | CHRISTINA BRACO |
| Grading Pre-Inspection | Cleared | 10/12/2023 | ALFREDO JARA |
| Construction near power lines | Cleared | 11/27/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/27/2023 | RIDWAN HARDY |
Contact Information
| Architect | Mehta,, Nita J; Lic. No.: C27172 | 21848 PROVIDENCIA STREET WOODLAND HILLS, CA 91364 |
| Contractor | Ind Construction Llc; Lic. No.: 937833-B | , |
| Engineer | Mohammadi,, Saeid; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 ENCINO, CA 91316 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/28/2024 | Corrections Issued | RICHARD DOCKUS |
| PLUMBING-Rough | 4/15/2024 | Partial Approval | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 4/24/2024 | Approved | SCOTT FINNILA |
| Footing/Foundation/Slab | 4/24/2024 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2024 | Partial Approval | FREDDIE RIVERA |
| METHANE-Rough | 5/8/2024 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/23/2024 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/23/2024 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Rough | 5/23/2024 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 5/23/2024 | Corrections Issued | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 6/10/2024 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 6/14/2024 | Partial Approval | BRENDAN MORELLI |
| Interior/Exterior Lathing | 7/15/2024 | Corrections Issued | FREDDIE RIVERA |
| Interior/Exterior Lathing | 7/16/2024 | Conditional Approval | FREDDIE RIVERA |
| Insulation | 7/17/2024 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 7/17/2024 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2024 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 2/24/2025 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Rough | 2/24/2025 | Corrections Issued | FREDDIE RIVERA |
| Underground Mechanical | 2/24/2025 | Corrections Issued | FREDDIE RIVERA |
| Drywall Nailing | 3/4/2025 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 3/11/2025 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 6/9/2025 | No Access for Inspection | FREDDIE RIVERA |
| Final | 6/9/2025 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 6/9/2025 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 6/9/2025 | No Access for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 10/27/2025 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 10/27/2025 | Approved | FREDDIE RIVERA |
| Final | 10/27/2025 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Final | 10/27/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 10/27/2025 | Approved | FREDDIE RIVERA |
| Service/Power Release | 10/27/2025 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 10/27/2025 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 10/30/2025 | Approved | FREDDIE RIVERA |
| HVAC-Final | 10/30/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 10/30/2025 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 11/5/2025 | Partial Inspection | FREDDIE RIVERA |
| Final | 11/5/2025 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Final | 11/5/2025 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Final | 11/5/2025 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 11/5/2025 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 11/13/2025 | Approved | FREDDIE RIVERA |
| Special/Order Compliance | 11/13/2025 | Corrections Issued | FREDDIE RIVERA |
| Final | 12/2/2025 | OK to Issue CofO | FREDDIE RIVERA |