3213-3213 1/2 E MALABAR ST 90063

Certificate Information: 3213-3213 1/2 E MALABAR ST 90063

Application / Permit
23016-10000-22950
Plan Check / Job No.
B23LA12873
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert attached (to existing single-family dwelling) ground floor garage (476sf) to ADU per LAMC 12.22 A.33(c) AND (e). Enclose area below second floor landing (114sf) to enlarge ADU. All work done per engineering.
Permit Issued
Issued on 10/12/2023
Issuing Office
Current Status
CofO Issued on 8/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2023 APPLICANT
Assigned to Plan Check Engineer 7/20/2023 RICARDO RAMIREZ
Corrections Issued 7/21/2023 RICARDO RAMIREZ
Building Plans Picked Up 8/4/2023 APPLICANT
Applicant returned to address corrections 9/22/2023 CRISTINA SALAZAR
Plan Check Approved 10/12/2023 DANIEL SMILEY
Issued 10/12/2023 APPLICANT
CofO in Progress 8/20/2025 ALIZAH MAYAGOITIA
CofO Issued 8/22/2025 DEROLD HAUFF
Permit Finaled 8/22/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/19/2023 ALEXANDER HELFER
Address approval Cleared 9/29/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 10/2/2023 JEANIE LAM
Sewer availability Cleared 10/2/2023 JEANIE LAM

Contact Information

Architect Jaber,, Ali; Lic. No.: C38901 31351 BIRDELLA RD      MALIBU, CA 90265
Contractor Y V General Construction Company Inc; Lic. No.: 1013222-B 1522 S ANDREWS PL APT #102      LOS ANGELES, CA 90019
Engineer Mutis,, Franz; Lic. No.: C71963 1226 KRIST DR      HOUSTON, TX 77055

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/19/2023 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 10/19/2023 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 10/24/2023 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 10/30/2023 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 11/30/2023 Approved OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 11/30/2023 Corrections Issued OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 12/4/2023 Approved OSVALDO PARAMO
Wood Frame 12/4/2023 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 12/12/2023 Approved JUSTIN HAWLEY
Green Building Rough 12/12/2023 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 12/12/2023 Partial Approval JUSTIN HAWLEY
Insulation 12/18/2023 Approved OSVALDO PARAMO
Drywall Nailing 12/26/2023 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 12/26/2023 Approved ALIZAH MAYAGOITIA
Final 7/29/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 7/29/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 7/29/2025 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 7/29/2025 Approved ALIZAH MAYAGOITIA
Final 8/12/2025 Conditional Approval ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 8/12/2025 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 8/12/2025 Approved ALIZAH MAYAGOITIA
Final 8/20/2025 OK to Issue CofO ALIZAH MAYAGOITIA