2281 N CHEREMOYA AVE 90068

Certificate Information: 2281 N CHEREMOYA AVE 90068

Application / Permit
23016-10000-22781
Plan Check / Job No.
B23LA12798
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
-ePlan- Conversion of Rec Room under Garage to Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A) **SEE COMMENTS**
Permit Issued
Issued on 8/25/2023
Issuing Office
Current Status
Issued on 8/25/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/12/2023 APPLICANT
Assigned to Plan Check Engineer 7/19/2023 EDWIN ESPIN
Corrections Issued 7/19/2023 EDWIN ESPIN
Applicant returned to address corrections 8/17/2023 EDWIN ESPIN
Applicant returned to address corrections 8/21/2023 EDWIN ESPIN
Plan Check Approved 8/24/2023 EDWIN ESPIN
Issued 8/25/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/3/2023 CELINA MORENO
Sewer availability Cleared 8/3/2023 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 8/6/2023 AHMED AMARRAGY
Miscellaneous Cleared 8/15/2023 ALBERT TAM

Contact Information

Contractor Maven Associates Inc The; Lic. No.: 1085625-B       ,

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/21/2023 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 12/21/2023 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 12/21/2023 Approved STUART CHAPMAN
Gas Test 12/21/2023 Partial Approval STUART CHAPMAN
HVAC-Rough 12/21/2023 Approved STUART CHAPMAN
PLUMBING-Rough 12/21/2023 Approved STUART CHAPMAN
Sewer 12/21/2023 Approved STUART CHAPMAN
Underground Mechanical 12/21/2023 Not Ready for Inspection STUART CHAPMAN
Insulation 1/3/2024 Approved STUART CHAPMAN
Interior/Exterior Lathing 1/3/2024 Partial Approval STUART CHAPMAN
Drywall Nailing 1/11/2024 Approved ROY SPAULDING
Interior/Exterior Lathing 1/11/2024 Approved ROY SPAULDING
Shower Pan 1/11/2024 Approved ROY SPAULDING
Underground Mechanical 3/13/2024 Approved ROY SPAULDING
BUILDING-Rough-Frame 4/12/2024 Approved ROY SPAULDING
ELECTRICAL-Final 4/12/2024 Approved ROY SPAULDING
Final 4/12/2024 Partial Approval ROY SPAULDING
HVAC-Final 4/12/2024 Approved ROY SPAULDING
PLUMBING-Final 4/12/2024 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 4/12/2024 SGSOV Approved ROY SPAULDING
Smoke Detectors 4/12/2024 Approved ROY SPAULDING