12300 W PICO BLVD 90064

Certificate Information: 12300 W PICO BLVD 90064

Application / Permit
23016-10000-22744
Plan Check / Job No.
B23LA12770
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Grocery Store
Work Description
eplan- Change of use from parking garage to retail grocery store. Reduction of registered number of parking for the existing commercial building due to AB 2097; Parking restripe
Permit Issued
Issued on 2/13/2024
Issuing Office
Current Status
CofO Issued on 12/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/14/2023 APPLICANT
Assigned to Plan Check Engineer 7/27/2023 SELLA BENYAMIN
Corrections Issued 8/8/2023 SELLA BENYAMIN
Quality Review Completed 8/21/2023 STEVEN KIM
Applicant returned to address corrections 1/11/2024 SELLA BENYAMIN
Applicant returned to address corrections 2/1/2024 SELLA BENYAMIN
Plan Check Approved 2/9/2024 SELLA BENYAMIN
No Progress 2/13/2024 SELLA BENYAMIN
Plan Check Approved 2/13/2024 SELLA BENYAMIN
Issued 2/13/2024 APPLICANT
CofO in Progress 12/8/2025 FARHAD DADBIN
Permit Finaled 12/9/2025 DAVID TSAU
CofO Issued 12/9/2025 DAVID TSAU
Permit Finaled 12/9/2025 DAVID TSAU

Permit Application Clearance Information

ZI Cleared 10/4/2023 DANIEL CORONADO
ZI Cleared 10/4/2023 DANIEL CORONADO
DAS Clearance Cleared 10/26/2023 Pranita Shah
Eng Process Fee Ord 176,300 Cleared 11/1/2023 DINAH GARIN
Sewer availability Cleared 11/1/2023 DINAH GARIN
Miscellaneous Cleared 12/18/2023 ALESSANDRO MERCURI
ZI Cleared 1/2/2024 JULISSA LOPEZ-HODOYAN

Contact Information

Architect Ko,, Michael Myungsoo; Lic. No.: NA22356       ,
Contractor Owner-Builder       ,

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/7/2025 Approved FARHAD DADBIN
Excavation/Setback/Form/Re-Bar 3/28/2025 Partial Approval FARHAD DADBIN
Final 4/18/2025 Not Ready for Inspection FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 4/18/2025 SGSOV Not Ready FARHAD DADBIN
Smoke Detectors 4/18/2025 Not Ready for Inspection FARHAD DADBIN
Final 6/27/2025 Not Ready for Inspection FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 6/27/2025 SGSOV Approved FARHAD DADBIN
Smoke Detectors 6/27/2025 Approved FARHAD DADBIN
Final 10/1/2025 Not Ready for Inspection FARHAD DADBIN
Final 12/4/2025 OK to Issue CofO FARHAD DADBIN