5212 W 21ST ST 90016
Certificate Information: 5212 W 21ST ST 90016
- Application / Permit
- 23016-10000-22695
- Plan Check / Job No.
- B23LA12736
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU (324 SF) PER STATE LAW.
- Permit Issued
- Issued on 11/29/2023
- Issuing Office
- Current Status
- CofO Issued on 9/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2023 | RICARDO RAMIREZ |
| Corrections Issued | 7/21/2023 | RICARDO RAMIREZ |
| Building Plans Picked Up | 7/27/2023 | APPLICANT |
| Applicant returned to address corrections | 11/14/2023 | MINA HABILI |
| Applicant returned to address corrections | 11/15/2023 | JOSEPH RAFOLS |
| Plan Check Approved | 11/29/2023 | ADAM HEGAZI |
| Issued | 11/29/2023 | APPLICANT |
| CofO in Progress | 8/6/2025 | ARTHUR NEGRETE |
| No Progress | 9/1/2025 | DEROLD HAUFF |
| CofO in Progress | 9/1/2025 | DEROLD HAUFF |
| CofO Issued | 9/5/2025 | DEROLD HAUFF |
| Permit Finaled | 9/5/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 7/27/2023 | NEIL TUANO |
| Address approval | Cleared | 7/28/2023 | NEIL TUANO |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2023 | NEIL TUANO |
| Construction near power lines | Cleared | 11/14/2023 | OSCAR CASTRO |
| Roof/Waste drainage to street | Cleared | 11/16/2023 | DAVID VO |
Contact Information
| Contractor | Wellman & Company; Lic. No.: 1053612-B | 12931 VENICE BLVD LOS ANGELES, CA 90066 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/30/2024 | Partial Approval | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 2/21/2024 | Corrections Issued | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 4/3/2024 | Not Ready for Inspection | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 4/16/2024 | Approved | RICHARD DOCKUS |
| Deputy Wood Construction | 7/31/2024 | Conditional Approval | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 8/7/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Rough | 8/7/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Special/Order Compliance | 8/7/2024 | Partial Approval | NICHOLAS LOPEZ |
| Verify Sprinkler Sign Off | 8/7/2024 | Approved | AMIR NAZARIAN |
| Wood Frame | 8/7/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 8/19/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 8/19/2024 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Rough | 8/19/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 9/6/2024 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 9/6/2024 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 9/6/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 9/6/2024 | Approved | ARTHUR NEGRETE |
| Insulation | 9/6/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 9/6/2024 | Approved | ARTHUR NEGRETE |
| Sewer | 9/6/2024 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 9/26/2024 | Approved | ANTHONY RAMOS |
| Shower Pan | 9/26/2024 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 10/1/2024 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 10/11/2024 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 1/14/2025 | Corrections Issued | ARTHUR NEGRETE |
| Final | 2/18/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 2/18/2025 | Approved | ARTHUR NEGRETE |
| Green Building Final | 2/18/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 2/18/2025 | SGSOV Approved | ARTHUR NEGRETE |
| Service/Power Release | 2/18/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Smoke Detectors | 2/18/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 2/24/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 2/24/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 2/24/2025 | Approved | ARTHUR NEGRETE |
| Final | 3/3/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Final | 3/3/2025 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 3/3/2025 | Approved | ARTHUR NEGRETE |
| Special/Order Compliance | 3/3/2025 | Partial Inspection | ALEX COLIN |
| Final | 8/5/2025 | OK to Issue CofO | ARTHUR NEGRETE |