305 E ROSE AVE 90291
Certificate Information: 305 E ROSE AVE 90291
- Application / Permit
- 23016-10000-22693
- Plan Check / Job No.
- B23LA12732
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (6) Church
- Work Description
- Permit to add the concrete wall to the existing URM stem walls. No change in architectural plans and floor area. Supplemental to permit 22016-10000-16725.
- Permit Issued
- Issued on 8/10/2023
- Issuing Office
- Current Status
- Permit Finaled on 12/13/2023
Permit Application Status History
| Submitted | 7/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2023 | QUAN NGHIEM |
| Corrections Issued | 7/18/2023 | QUAN NGHIEM |
| Quality Review Completed | 7/19/2023 | PETER KIM |
| Plan Check Approved | 8/9/2023 | QUAN NGHIEM |
| Issued | 8/10/2023 | APPLICANT |
| Permit Finaled | 12/13/2023 | FARHAD DADBIN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Caldeco Inc; Lic. No.: 563725-B | 23534 CALIFA STREET WOODLAND HILLS, CA 91367 |
| Engineer | Van, Valkenburg, John; Lic. No.: S5932 | 13259 KISMET AVE SYLMAR, CA 91342 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/11/2023 | Conditional Approval | FARHAD DADBIN |
| Excavation/Setback/Form/Re-Bar | 9/12/2023 | Approved | AMANUEL BERHE |
| Deputy Shotcrete | 10/4/2023 | Conditional Approval | FARHAD DADBIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2023 | Approved | FARHAD DADBIN |
| Wood Frame | 10/31/2023 | Partial Approval | FARHAD DADBIN |
| Final | 12/6/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Smoke Detectors | 12/6/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 12/13/2023 | Permit Finaled | FARHAD DADBIN |
| Smoke Detectors | 12/13/2023 | Approved | FARHAD DADBIN |