2764 S COLBY AVE 90064

Certificate Information: 2764 S COLBY AVE 90064

Application / Permit
23016-10000-22590
Plan Check / Job No.
B23LA12665
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* REMODEL OF (E) 1-STORY SFD.
Permit Issued
Issued on 11/15/2023
Issuing Office
Current Status
Permit Finaled on 8/20/2025

Permit Application Status History

Submitted 7/11/2023 APPLICANT
Assigned to Plan Check Engineer 7/27/2023 VIVIAN LAO
Corrections Issued 8/2/2023 VIVIAN LAO
Quality Review Completed 8/3/2023 GARO TELMI
Applicant returned to address corrections 9/1/2023 VIVIAN LAO
Plan Check Approved 9/19/2023 VIVIAN LAO
Issued 11/15/2023 APPLICANT
Permit Finaled 8/20/2025 KIRK SANDERS

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Keck,, Krystyan Elizabeth; Lic. No.: NA29385       ,
Contractor Aguirre Construction Inc; Lic. No.: 1019578-B       ,
Engineer Lotfi,, Fariborz F; Lic. No.: NA49359       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/4/2024 Conditional Approval JESUS PINEDA
Footing/Foundation/Slab 7/26/2024 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 10/29/2024 Corrections Issued KIRK SANDERS
Deputy Steel/Welding 10/30/2024 Conditional Approval DANIEL VERA
BUILDING-Rough-Frame 11/8/2024 Approved DANIEL VERA
Interior/Exterior Lathing 11/8/2024 Partial Approval DANIEL VERA
Wood Frame 11/8/2024 Approved DANIEL VERA
Insulation 11/14/2024 Approved REGINA MENDEZ
Drywall Nailing 11/27/2024 Approved DANIEL VERA
Shower Pan 11/27/2024 Approved DANIEL VERA
Interior/Exterior Lathing 12/16/2024 Approved REGINA MENDEZ
Pre-Inspection 12/16/2024 Partial Inspection JAYLIN GRAVITTE
Special/Order Compliance 12/16/2024 Partial Inspection BOBBY KEY
ELECTRICAL-Final 7/24/2025 Corrections Issued BOBBY KEY
Final 7/24/2025 Not Ready for Inspection BOBBY KEY
HVAC-Final 7/24/2025 Corrections Issued BOBBY KEY
PLUMBING-Final 7/24/2025 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 7/24/2025 SGSOV Approved BOBBY KEY
Smoke Detectors 7/24/2025 Approved BOBBY KEY
ELECTRICAL-Final 8/20/2025 Approved KIRK SANDERS
Final 8/20/2025 Permit Finaled KIRK SANDERS
HVAC-Final 8/20/2025 Approved KIRK SANDERS
PLUMBING-Final 8/20/2025 Approved KIRK SANDERS