5449 S VICTORIA AVE 90043
Certificate Information: 5449 S VICTORIA AVE 90043
- Application / Permit
- 23016-10000-22571
- Plan Check / Job No.
- B23LA12657
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- **ePlan** Enclose (E) Covered Porch And Interior Remodel To (E) Single Story Single Family Dwelling
- Permit Issued
- Issued on 7/22/2023
- Issuing Office
- Current Status
- Permit Finaled on 4/30/2025
Permit Application Status History
| Submitted | 7/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2023 | JASON JANGADA |
| Corrections Issued | 7/16/2023 | JASON JANGADA |
| Plan Check Approved | 7/21/2023 | EDWIN ESPIN |
| Issued | 7/22/2023 | APPLICANT |
| Permit Finaled | 4/29/2025 | LUIS CASTRO |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2023 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/16/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/13/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 12/13/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Wood Frame | 12/13/2023 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 2/15/2024 | No Access for Inspection | STUART CHAPMAN |
| ELECTRICAL-Rough | 2/15/2024 | No Access for Inspection | STUART CHAPMAN |
| Green Building Rough | 2/15/2024 | No Access for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 2/15/2024 | No Access for Inspection | STUART CHAPMAN |
| ELECTRICAL-Rough | 2/23/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 2/23/2024 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 2/23/2024 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 3/19/2024 | No Access for Inspection | ANTHONY EGSON |
| Green Building Rough | 3/19/2024 | No Access for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/4/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/4/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 4/4/2024 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 4/4/2024 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/26/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/26/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 4/26/2024 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 4/26/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 7/2/2024 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 7/2/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 7/2/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 7/2/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 7/2/2024 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 7/10/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 7/10/2024 | Approved | ANTHONY EGSON |
| Green Building Rough | 7/10/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 7/10/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 7/10/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 7/24/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 7/24/2024 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/1/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 8/1/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Wood Frame | 8/1/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 8/5/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 8/6/2024 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 8/6/2024 | Approved | ANTHONY EGSON |
| Insulation | 8/23/2024 | Partial Approval | ANTHONY EGSON |
| Interior/Exterior Lathing | 8/23/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2024 | Corrections Issued | JOSE MACIAS |
| Insulation | 8/30/2024 | Approved | JOSE MACIAS |
| Shower Pan | 8/30/2024 | Corrections Issued | JOSE MACIAS |
| BUILDING-Rough-Frame | 9/5/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2024 | Approved | ANTHONY EGSON |
| Green Building Rough | 9/5/2024 | Approved | ANTHONY EGSON |
| Insulation | 9/5/2024 | Approved | ANTHONY EGSON |
| Shower Pan | 9/5/2024 | Corrections Issued | ANTHONY EGSON |
| Insulation | 9/9/2024 | Approved | ALEX COLIN |
| Shower Pan | 9/9/2024 | Approved | ALEX COLIN |
| Drywall Nailing | 9/16/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 9/16/2024 | Partial Approval | ANTHONY EGSON |
| Interior/Exterior Lathing | 9/18/2024 | Approved | ANTHONY EGSON |
| Final | 4/29/2025 | Permit Finaled | LUIS CASTRO |
| Green Building Final | 4/29/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 4/29/2025 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 4/29/2025 | Approved | LUIS CASTRO |