5449 S VICTORIA AVE 90043

Certificate Information: 5449 S VICTORIA AVE 90043

Application / Permit
23016-10000-22571
Plan Check / Job No.
B23LA12657
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
**ePlan** Enclose (E) Covered Porch And Interior Remodel To (E) Single Story Single Family Dwelling
Permit Issued
Issued on 7/22/2023
Issuing Office
Current Status
Permit Finaled on 4/30/2025

Permit Application Status History

Submitted 7/10/2023 APPLICANT
Assigned to Plan Check Engineer 7/14/2023 JASON JANGADA
Corrections Issued 7/16/2023 JASON JANGADA
Plan Check Approved 7/21/2023 EDWIN ESPIN
Issued 7/22/2023 APPLICANT
Permit Finaled 4/29/2025 LUIS CASTRO

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 8/14/2023 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 8/16/2023 Approved ANTHONY EGSON
BUILDING-Rough-Frame 12/13/2023 Corrections Issued ANTHONY EGSON
Green Building Rough 12/13/2023 Not Ready for Inspection ANTHONY EGSON
Wood Frame 12/13/2023 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 2/15/2024 No Access for Inspection STUART CHAPMAN
ELECTRICAL-Rough 2/15/2024 No Access for Inspection STUART CHAPMAN
Green Building Rough 2/15/2024 No Access for Inspection STUART CHAPMAN
PLUMBING-Rough 2/15/2024 No Access for Inspection STUART CHAPMAN
ELECTRICAL-Rough 2/23/2024 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 2/23/2024 Corrections Issued ANTHONY EGSON
Green Building Rough 2/23/2024 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 2/23/2024 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 3/19/2024 No Access for Inspection ANTHONY EGSON
Green Building Rough 3/19/2024 No Access for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 4/4/2024 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 4/4/2024 Corrections Issued ANTHONY EGSON
Green Building Rough 4/4/2024 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 4/4/2024 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 4/26/2024 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 4/26/2024 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 4/26/2024 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 4/26/2024 Approved ANTHONY EGSON
BUILDING-Rough-Frame 7/2/2024 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 7/2/2024 Corrections Issued ANTHONY EGSON
Green Building Rough 7/2/2024 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 7/2/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 7/2/2024 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 7/10/2024 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 7/10/2024 Approved ANTHONY EGSON
Green Building Rough 7/10/2024 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 7/10/2024 Approved ANTHONY EGSON
PLUMBING-Rough 7/10/2024 Approved ANTHONY EGSON
BUILDING-Rough-Frame 7/24/2024 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 7/24/2024 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 8/1/2024 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 8/1/2024 Not Ready for Inspection ANTHONY EGSON
Wood Frame 8/1/2024 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 8/5/2024 Not Ready for Inspection ANTHONY EGSON
Interior/Exterior Lathing 8/6/2024 Corrections Issued ANTHONY EGSON
Wood Frame 8/6/2024 Approved ANTHONY EGSON
Insulation 8/23/2024 Partial Approval ANTHONY EGSON
Interior/Exterior Lathing 8/23/2024 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 8/30/2024 Corrections Issued JOSE MACIAS
Insulation 8/30/2024 Approved JOSE MACIAS
Shower Pan 8/30/2024 Corrections Issued JOSE MACIAS
BUILDING-Rough-Frame 9/5/2024 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 9/5/2024 Approved ANTHONY EGSON
Green Building Rough 9/5/2024 Approved ANTHONY EGSON
Insulation 9/5/2024 Approved ANTHONY EGSON
Shower Pan 9/5/2024 Corrections Issued ANTHONY EGSON
Insulation 9/9/2024 Approved ALEX COLIN
Shower Pan 9/9/2024 Approved ALEX COLIN
Drywall Nailing 9/16/2024 Approved ANTHONY EGSON
Interior/Exterior Lathing 9/16/2024 Partial Approval ANTHONY EGSON
Interior/Exterior Lathing 9/18/2024 Approved ANTHONY EGSON
Final 4/29/2025 Permit Finaled LUIS CASTRO
Green Building Final 4/29/2025 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 4/29/2025 SGSOV Approved LUIS CASTRO
Smoke Detectors 4/29/2025 Approved LUIS CASTRO