3187 S BENTLEY AVE 90034

Certificate Information: 3187 S BENTLEY AVE 90034

Application / Permit
23016-10000-22535
Plan Check / Job No.
B23LA12636
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Convert existing detached garage into ADU per GCS 65852.2(e)(1)(A). Design per WFPP.
Permit Issued
Issued on 5/20/2024
Issuing Office
Current Status
CofO Issued on 6/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/10/2023 APPLICANT
Assigned to Plan Check Engineer 7/14/2023 JOHNPAUL ISIP
Corrections Issued 7/15/2023 JOHNPAUL ISIP
Applicant returned to address corrections 5/8/2024 JOHNPAUL ISIP
Plan Check Approved 5/15/2024 CAROLEAN BASMA
Issued 5/20/2024 APPLICANT
CofO in Progress 6/21/2025 MICHAEL PELHAM
Permit Finaled 6/23/2025 RICHARD STEINBACH
Permit Finaled 6/23/2025 RICHARD STEINBACH
CofO Issued 6/23/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 9/5/2023 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 9/5/2023 HISASHI KOBAYAKAWA
Sewer availability Cleared 9/5/2023 HISASHI KOBAYAKAWA
Specific Plan Cleared 1/17/2024 PEDRO AYALA
Grading Pre-Inspection Cleared 1/25/2024 MICHAEL TEMPLE
Construction near power lines Cleared 4/22/2024 ENRIQUE ACOSTA

Contact Information

Contractor Foster D A Construction; Lic. No.: 673613-B       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/15/2024 Approved DANIEL VERA
Underground Mechanical 10/15/2024 Approved DANIEL VERA
Underground Mechanical 10/17/2024 Approved DANIEL VERA
Drywall Nailing 10/21/2024 Partial Approval DANIEL VERA
Interior/Exterior Lathing 10/21/2024 Not Ready for Inspection DANIEL VERA
Insulation 10/22/2024 Not Ready for Inspection DANIEL VERA
Footing/Foundation/Slab 10/24/2024 Approved DANIEL VERA
Insulation 10/24/2024 Partial Approval DANIEL VERA
Insulation 11/14/2024 Approved REGINA MENDEZ
Floor/Roof Diaphrgm/Shear Wall 12/6/2024 Partial Approval BOBBY KEY
ELECTRICAL-Rough 1/3/2025 Approved DANIEL VERA
PLUMBING-Rough 1/3/2025 Approved DANIEL VERA
BUILDING-Rough-Frame 1/10/2025 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 1/10/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 1/10/2025 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 1/28/2025 Approved EVAN COOPER
Green Building Rough 1/28/2025 Approved EVAN COOPER
MERV13>=Rough 1/28/2025 Approved EVAN COOPER
Shower Pan 1/28/2025 Approved EVAN COOPER
Verify Sprinkler Sign Off 1/28/2025 Approved EVAN COOPER
Insulation 1/30/2025 Approved EVAN COOPER
Drywall Nailing 2/4/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 2/4/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 2/21/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Final 2/25/2025 Approved JESUS RODRIGUEZ
PLUMBING-Final 2/25/2025 Partial Approval JESUS RODRIGUEZ
HVAC-Final 2/27/2025 Corrections Issued EVAN COOPER
PLUMBING-Final 3/3/2025 Approved DANIEL VERA
Special/Order Compliance 3/3/2025 Approved WILBER ROSALES
HVAC-Final 3/20/2025 Approved KIRK SANDERS
Final 4/25/2025 Corrections Issued ARAM AVEDISIAN
Green Building Final 4/25/2025 Approved ARAM AVEDISIAN
MERV13>=Final 4/25/2025 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 4/25/2025 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 4/25/2025 Approved ARAM AVEDISIAN
Service/Power Release 5/9/2025 Approved MICHAEL PELHAM
Final 6/21/2025 OK to Issue CofO MICHAEL PELHAM