1534 1/2 S MEADOWBROOK AVE 90019

Certificate Information: 1534 1/2 S MEADOWBROOK AVE 90019

Application / Permit
23016-10000-22410
Plan Check / Job No.
B23LA12559
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Convert (E) 4 car garage to One Accessory Dwelling Unit per LAMC 12.22 A.33 (c)-(d). All work per Wood Frame Prescriptive Provisions
Permit Issued
Issued on 8/31/2023
Issuing Office
Current Status
CofO Issued on 9/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/10/2023 APPLICANT
Assigned to Plan Check Engineer 7/14/2023 JASON JANGADA
Corrections Issued 7/16/2023 JASON JANGADA
Applicant returned to address corrections 8/8/2023 JASON JANGADA
Applicant returned to address corrections 8/19/2023 EDWIN ESPIN
Plan Check Approved 8/23/2023 EDWIN ESPIN
Issued 8/31/2023 APPLICANT
CofO in Progress 9/19/2025 ARTHUR NEGRETE
Permit Finaled 9/21/2025 DEROLD HAUFF
CofO Issued 9/21/2025 DEROLD HAUFF
Permit Finaled 9/21/2025 DEROLD HAUFF

Permit Application Clearance Information

Tenant Habitability Plan Cleared 7/31/2023 RICARDO BOHORQUEZ
Address approval Cleared 8/3/2023 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 8/4/2023 JESSICA OPINION
Sewer availability Cleared 8/4/2023 JESSICA OPINION

Contact Information

Contractor Owner-Builder       ,
Engineer Maftoon,, Jay; Lic. No.: M26139 18340 VENTURA BLVD STE 227      TARZANA, CA 91356

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/22/2024 Approved RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 3/19/2024 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 3/19/2024 Partial Approval STUART CHAPMAN
PLUMBING-Rough 3/19/2024 Partial Approval STUART CHAPMAN
Pre-Inspection 3/19/2024 Partial Inspection STUART CHAPMAN
Underground Mechanical 3/19/2024 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 4/29/2024 Corrections Issued ALIZAH MAYAGOITIA
Deputy Drilled-In Anchors 5/3/2024 Conditional Approval RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 5/9/2024 Approved RICHARD DOCKUS
Footing/Foundation/Slab 5/9/2024 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 5/29/2024 Partial Inspection ARTHUR NEGRETE
Green Building Rough 5/29/2024 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 5/29/2024 Approved ARTHUR NEGRETE
PLUMBING-Rough 6/10/2024 Corrections Issued RONNIE MINDANAO
Gas Test 6/11/2024 Approved ENRIQUE MIRELES
Underground Mechanical 6/11/2024 Approved ENRIQUE MIRELES
PLUMBING-Rough 6/13/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 6/17/2024 Approved ARTHUR NEGRETE
HVAC-Rough 6/17/2024 Approved ARTHUR NEGRETE
Insulation 6/24/2024 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 6/27/2024 Approved RICHARD DOCKUS
Underground Mechanical 6/28/2024 Approved JOAQUIN GREENOUGH
Drywall Nailing 7/8/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Final 7/30/2024 Corrections Issued BRENDAN MORELLI
BUILDING-Rough-Frame 8/20/2024 Approved ARTHUR NEGRETE
Final 8/20/2024 Not Ready for Inspection ARTHUR NEGRETE
Green Building Final 8/20/2024 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 8/20/2024 SGSOV Approved ARTHUR NEGRETE
Smoke Detectors 8/20/2024 Approved ARTHUR NEGRETE
Final 2/21/2025 Partial Approval ARTHUR NEGRETE
ELECTRICAL-Final 8/26/2025 Approved ARTHUR NEGRETE
Final 8/26/2025 Partial Approval ARTHUR NEGRETE
HVAC-Final 8/26/2025 Approved ARTHUR NEGRETE
PLUMBING-Final 8/26/2025 Approved ARTHUR NEGRETE
Final 9/4/2025 Conditional Approval ARTHUR NEGRETE
Final 9/19/2025 OK to Issue CofO ARTHUR NEGRETE