1224 S BEVERWIL DR 90035
Certificate Information: 1224 S BEVERWIL DR 90035
- Application / Permit
- 23016-10000-22406
- Plan Check / Job No.
- B23LA12550
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (15) Telecommunication Transmitter - wireless
- Work Description
- ePlan: (PER ZA-1996-0443(CUZ)(PA1)) Proposal to co-locate a wireless telecommunications facility on rooftop. Antenna scope of work to include: (2) antenna screens, (3) panel antennas, (6) proposed RRUs, (3) proposed surge suppression devices, (3) power cables, (3) fiber cables. Equipment scope of work to include: (1) platform, (1) equipment cabinet, (1) BBU, (1) PPC, (1) Nema telco-fiber box, (1) GPS Unit, (1) sub meter, (1) Cam-Lock, (1) MTS and disconnect switch, (1) step-down transformer.
- Permit Issued
- Issued on 10/3/2023
- Issuing Office
- Current Status
- Permit Finaled on 8/16/2024
Permit Application Status History
| Submitted | 7/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2023 | FERNANDO FLORES |
| Corrections Issued | 7/24/2023 | FERNANDO FLORES |
| Applicant returned to address corrections | 8/17/2023 | SAMUEL GONZALEZ |
| Plan Check Approved | 8/29/2023 | GEORGE ALVAREZ |
| Issued | 10/3/2023 | APPLICANT |
| Permit Finaled | 8/16/2024 | FARHAD DADBIN |
Permit Application Clearance Information
| Plan Approval | Cleared | 8/16/2023 | LESLIE PEREZ |
| ZA Case | Cleared | 8/16/2023 | LESLIE PEREZ |
| ZA Case | Cleared | 8/16/2023 | LESLIE PEREZ |
| ZA Case | Cleared | 8/16/2023 | LESLIE PEREZ |
| ZA Case | Cleared | 8/16/2023 | LESLIE PEREZ |
Contact Information
| Architect | Lara,, Robert Jerry; Lic. No.: C30334 | 2 SOUTH UNIVERSITY DRIVE # 245 PLANTATION, FL 33324 |
| Contractor | Process Cellular Inc; Lic. No.: 951819-B | 1391 SPECIALTY DRIVE SUITE A VISTA, CA 92081 |
| Engineer | Haile,, Theodros; Lic. No.: C81056 | 10519 NE 67TH AVE VANCOUVER, WA 98686 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Structural Steel Frame | 5/2/2024 | Partial Approval | FARHAD DADBIN |
| Final | 8/16/2024 | Permit Finaled | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 8/16/2024 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 8/16/2024 | Approved | FARHAD DADBIN |