8848 N GOTHIC AVE 1-3 91343
Certificate Information: 8848 N GOTHIC AVE 1-3 91343
- Application / Permit
- 23016-10000-22324
- Plan Check / Job No.
- B23LA12501
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Conversion of 1050 SF portion of SFD with addition (145 SF) to (N) attached ADU per GCS 65852.2(e)(1)(A). Conversion of 368 SF attached garage to (N) JADU per 65852.2(e)(1)(A) and 65852.22.
- Permit Issued
- Issued on 6/28/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2023 | ZAW HAN |
| Corrections Issued | 7/13/2023 | ZAW HAN |
| Building Plans Picked Up | 7/14/2023 | APPLICANT |
| Plan Check Approved | 3/12/2024 | HUAN LE |
| Plan Check Approved | 3/12/2024 | ADAM HEGAZI |
| Issued | 6/28/2024 | APPLICANT |
| CofO in Progress | 4/22/2025 | JACK KARGODORIAN |
| Permit Finaled | 5/6/2025 | RUBEN SALAS |
| CofO Issued | 5/6/2025 | RUBEN SALAS |
| Permit Finaled | 5/6/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/14/2023 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 7/14/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 7/14/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2023 | TAL SHEMEN |
| Highway dedication | Cleared | 7/26/2023 | TAL SHEMEN |
| Construction near power lines | Cleared | 2/23/2024 | WALTER RAMIREZ |
| Construction within easement | Cleared | 2/23/2024 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/19/2024 | No Access for Inspection | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 7/23/2024 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 7/25/2024 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 8/23/2024 | Partial Approval | RAUL OLAGI |
| Sewer | 8/23/2024 | Approved | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 8/30/2024 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 8/30/2024 | Approved | RAUL OLAGI |
| Underground Mechanical | 8/30/2024 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Rough | 9/4/2024 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Rough | 9/6/2024 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 9/9/2024 | No Access for Inspection | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2024 | Partial Approval | JOSE AVILA |
| HVAC-Rough | 9/27/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 9/27/2024 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 10/2/2024 | No Access for Inspection | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 10/15/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 10/15/2024 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 10/15/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 10/15/2024 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 10/21/2024 | Approved | SALVADOR MARTINEZ |
| HVAC-Rough | 10/21/2024 | Approved | SALVADOR MARTINEZ |
| Underground Mechanical | 10/21/2024 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 10/24/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/24/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/31/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Rough | 10/31/2024 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 10/31/2024 | Partial Approval | SALVADOR MARTINEZ |
| Wood Frame | 10/31/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 12/2/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Deputy Drilled-In Anchors | 12/20/2024 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 1/7/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 1/7/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Insulation | 1/7/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Shower Pan | 1/7/2025 | Approved | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 1/10/2025 | Partial Inspection | SALVADOR MARTINEZ |
| Drywall Nailing | 1/21/2025 | Partial Approval | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 1/21/2025 | Approved | SALVADOR MARTINEZ |
| Drywall Nailing | 1/27/2025 | Partial Approval | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 1/27/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 1/30/2025 | Partial Approval | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 1/30/2025 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 2/4/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Drywall Nailing | 2/4/2025 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 4/3/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 4/3/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 4/3/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 4/3/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Final | 4/3/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 4/3/2025 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 4/3/2025 | SGSOV Not Ready | SALVADOR MARTINEZ |
| Smoke Detectors | 4/3/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 4/10/2025 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 4/10/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 4/10/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 4/10/2025 | Approved | SALVADOR MARTINEZ |
| HVAC-Final | 4/10/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 4/10/2025 | Approved | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 4/10/2025 | SGSOV Approved | SALVADOR MARTINEZ |
| Smoke Detectors | 4/10/2025 | Approved | SALVADOR MARTINEZ |
| Final | 4/16/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 4/21/2025 | OK to Issue CofO | JACK KARGODORIAN |