145-147 1/2 E AVENUE 44 90031
Certificate Information: 145-147 1/2 E AVENUE 44 90031
- Application / Permit
- 23016-10000-22246
- Plan Check / Job No.
- B23LA12451
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Convert existing 355 SF storage room into a new one bedroom ADU PER CA Govt. Code 65852.2(e)(1)(C)
- Permit Issued
- Issued on 9/5/2023
- Issuing Office
- Current Status
- CofO Issued on 3/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2023 | KHUONG TRUONG |
| Corrections Issued | 7/16/2023 | KHUONG TRUONG |
| Applicant returned to address corrections | 8/26/2023 | SHANGQIN XIE |
| Plan Check Approved | 8/30/2023 | SHANGQIN XIE |
| Issued | 9/5/2023 | APPLICANT |
| CofO in Progress | 2/28/2024 | ALIZAH MAYAGOITIA |
| Permit Finaled | 3/8/2024 | DEROLD HAUFF |
| CofO Issued | 3/8/2024 | DEROLD HAUFF |
| Permit Finaled | 3/8/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/1/2023 | CHRISTINA BRACO |
| Sewer availability | Cleared | 8/1/2023 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2023 | CHRISTINA BRACO |
| HPOZ | Cleared | 8/28/2023 | MICAELA TORRES-GIL |
Contact Information
| Contractor | Fort Multifamily Inc; Lic. No.: 1097435-B | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/18/2023 | Corrections Issued | OSVALDO PARAMO |
| Wood Frame | 9/18/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Rough | 9/22/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Wood Frame | 9/22/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 9/27/2023 | Approved | OSVALDO PARAMO |
| Green Building Rough | 11/6/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Wood Frame | 11/6/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Rough | 11/14/2023 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 11/14/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Wood Frame | 11/14/2023 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 11/17/2023 | Approved | JOSH MEISTER |
| Drywall Nailing | 11/21/2023 | Approved | OSVALDO PARAMO |
| Final | 1/2/2024 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 1/2/2024 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 1/2/2024 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 1/2/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 1/12/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 1/12/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 2/28/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |