7407 W 91ST ST 90045

Certificate Information: 7407 W 91ST ST 90045

Application / Permit
23016-10000-22220
Plan Check / Job No.
B23LA12436
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. STRUCTURAL RENOVATION OF (E) 2,103 SF SFD PER ENGRS CALCS
Permit Issued
Issued on 8/11/2023
Issuing Office
Current Status
Permit Finaled on 11/26/2024

Permit Application Status History

Submitted 7/18/2023 APPLICANT
Assigned to Plan Check Engineer 7/26/2023 AMY GUEVARRA
Corrections Issued 7/27/2023 AMY GUEVARRA
Plan Check Approved 8/10/2023 AMY GUEVARRA
Issued 8/11/2023 APPLICANT
Permit Finaled 11/26/2024 TEMISTOCLES CAAL

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/8/2023 SERGIO VALENZUELA

Contact Information

Contractor Owner-Builder       ,
Engineer Kiledjian,, George Zohrab; Lic. No.: C74761 11447 VIKING AVE      NORTHRIDGE, CA 91326

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 9/29/2023 Partial Approval BOBBY KEY
Footing/Foundation/Slab 12/29/2023 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 1/4/2024 Conditional Approval BOBBY KEY
BUILDING-Rough-Frame 1/23/2024 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Rough 1/23/2024 Corrections Issued BOBBY KEY
HVAC-Rough 1/23/2024 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 1/23/2024 Conditional Approval BOBBY KEY
ELECTRICAL-Rough 1/29/2024 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 2/20/2024 Not Ready for Inspection BOBBY KEY
Footing/Foundation/Slab 2/20/2024 Approved BOBBY KEY
HVAC-Rough 2/20/2024 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 2/23/2024 Approved BOBBY KEY
HVAC-Rough 2/23/2024 Approved BOBBY KEY
Green Building Rough 3/11/2024 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 3/11/2024 Not Ready for Inspection BOBBY KEY
Interior/Exterior Lathing 3/15/2024 Partial Inspection BOBBY KEY
BUILDING-Rough-Frame 3/18/2024 Conditional Approval BOBBY KEY
Interior/Exterior Lathing 3/18/2024 Partial Approval BOBBY KEY
Insulation 3/28/2024 Approved BOBBY KEY
Drywall Nailing 4/12/2024 Partial Approval BOBBY KEY
Shower Pan 4/12/2024 Corrections Issued BOBBY KEY
Shower Pan 4/17/2024 Approved RICHARD STEINBACH
ELECTRICAL-Final 11/7/2024 Corrections Issued TEMISTOCLES CAAL
Final 11/7/2024 Corrections Issued TEMISTOCLES CAAL
Green Building Final 11/7/2024 Corrections Issued TEMISTOCLES CAAL
HVAC-Final 11/7/2024 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Final 11/7/2024 Corrections Issued TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 11/7/2024 SGSOV Approved TEMISTOCLES CAAL
Smoke Detectors 11/7/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 11/8/2024 Corrections Issued TEMISTOCLES CAAL
Final 11/8/2024 Corrections Issued TEMISTOCLES CAAL
HVAC-Final 11/8/2024 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Final 11/8/2024 Corrections Issued TEMISTOCLES CAAL
ELECTRICAL-Final 11/22/2024 Corrections Issued TEMISTOCLES CAAL
Final 11/22/2024 Corrections Issued TEMISTOCLES CAAL
HVAC-Final 11/22/2024 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Final 11/22/2024 Corrections Issued TEMISTOCLES CAAL
ELECTRICAL-Final 11/26/2024 Approved TEMISTOCLES CAAL
Final 11/26/2024 Permit Finaled TEMISTOCLES CAAL
HVAC-Final 11/26/2024 Approved TEMISTOCLES CAAL
PLUMBING-Final 11/26/2024 Approved TEMISTOCLES CAAL