Deputy Drilled-In Anchors
|
11/2/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
11/6/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
11/8/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
11/8/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
11/9/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
11/9/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
11/13/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
11/13/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
11/14/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
11/14/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
11/15/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
11/15/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
11/16/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
11/17/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
11/17/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
11/20/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
11/20/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
11/21/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
11/21/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
11/22/2023
|
Approved
|
NICK LAROCCA
|
|
Deputy Reinf. Concrete
|
11/22/2023
|
Approved
|
NICK LAROCCA
|
|
Deputy Drilled-In Anchors
|
11/27/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
11/27/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
11/28/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
11/28/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
11/29/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
11/29/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
11/30/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
11/30/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
12/1/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
12/1/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
12/4/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
12/4/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
12/5/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
12/5/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
12/6/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
12/6/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
12/7/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
12/7/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
12/8/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
12/8/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
12/14/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
12/14/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
12/15/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
12/15/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Steel/Welding
|
12/15/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
12/18/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
12/18/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
12/19/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
12/19/2023
|
Partial Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
12/19/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Steel/Welding
|
12/19/2023
|
Partial Approval
|
ALAN NOVAK
|
|
Drywall Nailing
|
12/19/2023
|
Partial Approval
|
ALAN NOVAK
|
|
Light Gage Steel Frame
|
12/19/2023
|
Approved
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
12/20/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
12/20/2023
|
Partial Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
12/20/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Steel/Welding
|
12/20/2023
|
Partial Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
12/21/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
12/21/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
12/22/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
12/22/2023
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
12/27/2023
|
Approved
|
NICK LAROCCA
|
|
Deputy Reinf. Concrete
|
12/27/2023
|
Approved
|
NICK LAROCCA
|
|
Deputy Steel/Welding
|
12/27/2023
|
Approved
|
NICK LAROCCA
|
|
Reinforced Concrete Frame
|
12/27/2023
|
Partial Approval
|
NICK LAROCCA
|
|
Structural Steel Frame
|
12/27/2023
|
Partial Approval
|
NICK LAROCCA
|
|
Deputy Drilled-In Anchors
|
12/28/2023
|
Approved
|
NICK LAROCCA
|
|
Deputy Reinf. Concrete
|
12/28/2023
|
Approved
|
NICK LAROCCA
|
|
Deputy Drilled-In Anchors
|
12/29/2023
|
Approved
|
NICK LAROCCA
|
|
Deputy Reinf. Concrete
|
12/29/2023
|
Approved
|
NICK LAROCCA
|
|
Deputy Steel/Welding
|
12/29/2023
|
Approved
|
NICK LAROCCA
|
|
Deputy Drilled-In Anchors
|
1/2/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Structural Steel Frame
|
1/2/2024
|
Approved
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
1/3/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
1/4/2024
|
Approved
|
NICK LAROCCA
|
|
Deputy Drilled-In Anchors
|
1/5/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Fireproofing
|
1/5/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
1/8/2024
|
Approved
|
NICK LAROCCA
|
|
Deputy Drilled-In Anchors
|
1/9/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
1/10/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
1/11/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
1/12/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
1/16/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Light Gage Steel Frame
|
1/16/2024
|
Partial Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
1/17/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
1/18/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
1/19/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
1/22/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
1/23/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
1/24/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
1/25/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Fireproofing
|
1/25/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
1/26/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Drywall Nailing
|
2/1/2024
|
Approved
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
2/9/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Light Gage Steel Frame
|
2/20/2024
|
Partial Approval
|
ALAN NOVAK
|
|
Light Gage Steel Frame
|
3/4/2024
|
Approved
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
3/11/2024
|
Approved
|
NICK LAROCCA
|
|
Deputy Drilled-In Anchors
|
3/12/2024
|
Partial Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
3/13/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
3/14/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
3/15/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Light Gage Steel Frame
|
3/15/2024
|
Partial Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
3/18/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
3/19/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
3/20/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
3/21/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
3/22/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Drywall Nailing
|
3/28/2024
|
Partial Approval
|
ALAN NOVAK
|
|
Light Gage Steel Frame
|
4/5/2024
|
Partial Approval
|
NICK LAROCCA
|
|
Light Gage Steel Frame
|
4/8/2024
|
Approved
|
ALAN NOVAK
|
|
Excavation/Setback/Form/Re-Bar
|
5/21/2024
|
Partial Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
5/23/2024
|
Conditional Approval
|
ALAN NOVAK
|
|
Deputy Drilled-In Anchors
|
6/26/2024
|
Partial Approval
|
ALAN NOVAK
|
|
T-Bar Ceiling
|
7/16/2024
|
Approved
|
ALAN NOVAK
|
|
Structural Steel Frame
|
7/24/2024
|
Approved
|
ALAN NOVAK
|
|
Final
|
8/29/2024
|
Permit Finaled
|
ALAN NOVAK
|
|
Green Building Final
|
8/29/2024
|
Approved
|
ALAN NOVAK
|
|
SGSOV-Seismic Gas S/O Valve
|
8/29/2024
|
SGSOV Approved
|
ALAN NOVAK
|
|
Smoke Detectors
|
8/29/2024
|
Approved
|
ALAN NOVAK
|