1632 N COURTNEY AVE 90046
Certificate Information: 1632 N COURTNEY AVE 90046
- Application / Permit
- 23016-10000-22090
- Plan Check / Job No.
- B23LA12361
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL OF (E) 1-STORY SINGLE FAMILY DWELLING TO REMOVE AND REPLACE ALL EXISTING WINDOWS AND DOORS, REMODEL KITCHEN, AND ADD NEW SET OF STAIRS AND HANDRAIL LEADING TO THE BACKYARD. WORK DONE PER ENGINEER.
- Permit Issued
- Issued on 9/6/2023
- Issuing Office
- Current Status
- Issued on 9/6/2023
Permit Application Status History
| Submitted | 7/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2023 | MADISON ODELL |
| Corrections Issued | 7/11/2023 | MADISON ODELL |
| Applicant returned to address corrections | 8/2/2023 | MADISON ODELL |
| Applicant returned to address corrections | 8/19/2023 | MADISON ODELL |
| Plan Check Approved | 9/1/2023 | DANIEL YIP |
| Issued | 9/6/2023 | APPLICANT |
Permit Application Clearance Information
| HPOZ | Cleared | 8/31/2023 | ERIK VAN BREENE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Roberts,, Jeffrey Allan; Lic. No.: NA56881 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 9/19/2023 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 9/19/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 9/19/2023 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 10/19/2023 | Conditional Approval | STUART CHAPMAN |
| Insulation | 10/24/2023 | Approved | STUART CHAPMAN |
| Drywall Nailing | 11/28/2023 | Approved | RAUL BARAJAS |
| Drywall Nailing | 12/1/2023 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 12/1/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 12/1/2023 | Approved | STUART CHAPMAN |
| Final | 5/14/2024 | Partial Inspection | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 5/14/2024 | SGSOV Not Ready | BRIAN SULLIVAN |
| Smoke Detectors | 5/14/2024 | Partial Inspection | BRIAN SULLIVAN |
| Final | 5/17/2024 | Corrections Issued | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 5/17/2024 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 5/17/2024 | Approved | RAUL BARAJAS |
| Special/Order Compliance | 2/25/2026 | Corrections Issued | ROY SPAULDING |
| Special/Order Compliance | 2/26/2026 | Corrections Issued | ROY SPAULDING |
| Final | 3/13/2026 | Corrections Issued | ROY SPAULDING |