13302 W MOORPARK ST 91423
Certificate Information: 13302 W MOORPARK ST 91423
- Application / Permit
- 23016-10000-22057
- Plan Check / Job No.
- B23LA12337
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Office
- Work Description
- EPLAN Address is 13302 - 13308 Moorpark. Phase 2 expansion Tenant Improvement: Existing change of use remodel of Liquor Store to Dental office. New non-bearing interior walls, load bearing interior walls, drywall ceiling, doors, millwork and finishes. Addition of 1 accessible restroom. Replacement of 2 HVAC units on roof. Expansion Suite = 2,420 SF Existing dental office permit Phase 1 completed in 2020 under 19016-30000-30999 No parking required per emergency Ordinance 187096
- Permit Issued
- Issued on 2/15/2024
- Issuing Office
- Current Status
- CofO Issued on 8/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2023 | ARSALAN SHABESTARI |
| Corrections Issued | 7/31/2023 | ARSALAN SHABESTARI |
| Quality Review Completed | 8/10/2023 | FARUK SEZER |
| Plan Check Approved | 11/3/2023 | ARSALAN SHABESTARI |
| Issued | 2/15/2024 | APPLICANT |
| CofO in Progress | 8/5/2024 | STEVEN LEVITT |
| Permit Finaled | 8/8/2024 | JEFFREY DURAN |
| CofO Issued | 8/8/2024 | JEFFREY DURAN |
| Permit Finaled | 8/8/2024 | JEFFREY DURAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/15/2023 | COLIN LOREDO |
| "Q" conditions | Cleared | 8/28/2023 | NATHAN ROMINE |
| ZI | Cleared | 8/28/2023 | NATHAN ROMINE |
| Sewer availability | Cleared | 8/29/2023 | COLIN LOREDO |
| DAS Clearance | Cleared | 9/12/2023 | Sarkis Harabedian |
| Green Code | Cleared | 10/30/2023 | Sarkis Harabedian |
Contact Information
| Contractor | J R Development Inc; Lic. No.: 561978-B | , |
| Contractor | Mercury Construction; Lic. No.: 561978-B | , |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/26/2024 | Conditional Approval | JEFFREY DURAN |
| Excavation/Setback/Form/Re-Bar | 3/27/2024 | Approved | STEVEN LEVITT |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2024 | Approved | STEVEN LEVITT |
| Deputy Drilled-In Anchors | 4/24/2024 | Conditional Approval | KENNETH ROBERTS |
| Green Building Rough | 4/26/2024 | Approved | STEVEN LEVITT |
| Light Gage Steel Frame | 4/26/2024 | Approved | STEVEN LEVITT |
| Wood Frame | 4/26/2024 | Approved | STEVEN LEVITT |
| Deputy Wood Construction | 4/30/2024 | Conditional Approval | KENNETH ROBERTS |
| Insulation | 5/2/2024 | Approved | STEVEN LEVITT |
| Drywall Nailing | 5/7/2024 | Approved | STEVEN LEVITT |
| T-Bar Ceiling | 5/31/2024 | Approved | STEVEN LEVITT |
| Final | 7/25/2024 | OK to Issue CofO | STEVEN LEVITT |
| Green Building Final | 7/25/2024 | Approved | STEVEN LEVITT |
| SGSOV-Seismic Gas S/O Valve | 7/25/2024 | SGSOV Approved | STEVEN LEVITT |
| Smoke Detectors | 7/25/2024 | Approved | STEVEN LEVITT |