1825 3/4 S VAN NESS AVE 90019
Certificate Information: 1825 3/4 S VAN NESS AVE 90019
- Application / Permit
- 23016-10000-21880
- Plan Check / Job No.
- B23LA12258
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN CONVERT (E) GARAGE TO (N) A.D.U.
- Permit Issued
- Issued on 3/20/2024
- Issuing Office
- Current Status
- CofO Issued on 2/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/19/2023 | JOSEPH RAFOLS |
| Corrections Issued | 7/19/2023 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 8/24/2023 | ARSALAN SHABESTARI |
| Plan Check Approved | 8/26/2023 | ARSALAN SHABESTARI |
| Issued | 3/20/2024 | APPLICANT |
| CofO in Progress | 2/11/2026 | WILLIAM SIERRA |
| Permit Finaled | 2/14/2026 | DEROLD HAUFF |
| Permit Finaled | 2/14/2026 | DEROLD HAUFF |
| CofO Issued | 2/14/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/20/2023 | WALLIE JONG |
| Sewer availability | Cleared | 7/20/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2023 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 8/22/2023 | RAFAEL FONTES |
Contact Information
| Contractor | Melior Building Co; Lic. No.: 1078546-B | , |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/22/2024 | Approved | JEROME BLACKWOOD |
| METHANE-Rough | 5/3/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Wood Frame | 5/3/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Insulation | 7/11/2024 | Corrections Issued | JEROME BLACKWOOD |
| Floor/Roof Diaphrgm/Shear Wall | 1/2/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Insulation | 1/2/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| METHANE-Rough | 1/2/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Wood Frame | 1/2/2025 | Corrections Issued | WILLIAM SIERRA |
| Pre-Inspection | 3/21/2025 | Partial Inspection | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2025 | Corrections Issued | WILLIAM SIERRA |
| METHANE-Rough | 4/7/2025 | Approved | WILLIAM SIERRA |
| Wood Frame | 4/7/2025 | Corrections Issued | WILLIAM SIERRA |
| Wood Frame | 4/11/2025 | Corrections Issued | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2025 | Corrections Issued | WILLIAM SIERRA |
| Wood Frame | 4/17/2025 | Corrections Issued | WILLIAM SIERRA |
| Deputy Drilled-In Anchors | 4/25/2025 | Conditional Approval | WILLIAM SIERRA |
| Interior/Exterior Lathing | 4/29/2025 | Partial Approval | WILLIAM SIERRA |
| Special/Order Compliance | 4/29/2025 | Approved | WILLIAM SIERRA |
| Wood Frame | 4/29/2025 | Approved | WILLIAM SIERRA |
| Insulation | 5/2/2025 | Approved | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2025 | Approved | WILLIAM SIERRA |
| Drywall Nailing | 5/20/2025 | Approved | WILLIAM SIERRA |
| Final | 9/10/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 9/10/2025 | SGSOV Not Required | WILLIAM SIERRA |
| Smoke Detectors | 9/10/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Final | 2/10/2026 | OK to Issue CofO | WILLIAM SIERRA |
| Smoke Detectors | 2/10/2026 | Approved | WILLIAM SIERRA |