11315 W VENTURA BLVD 91604

Certificate Information: 11315 W VENTURA BLVD 91604

Application / Permit
23016-10000-21714
Plan Check / Job No.
B23LA12187
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
TENANT IMPROVEMENT AND CHANGE OF USE FROM RETAIL TO MARKET
Permit Issued
Issued on 2/22/2024
Issuing Office
Current Status
Permit Finaled on 10/4/2024

Permit Application Status History

Submitted 7/6/2023 APPLICANT
Assigned to Plan Check Engineer 7/6/2023 JOE VO
Corrections Issued 7/8/2023 JOE VO
Quality Review Completed 7/12/2023 GARO TELMI
Applicant returned to address corrections 12/18/2023 JOE VO
Plan Check Approved 1/31/2024 JOE VO
Issued 2/22/2024 APPLICANT
Permit Finaled 10/4/2024 STEVEN LEVITT

Permit Application Clearance Information

Sewer availability Cleared 7/28/2023 TAL SHEMEN
Address approval Cleared 7/31/2023 TAL SHEMEN
Specific Plan Cleared 12/19/2023 SPENCER WEJROWSKI
ZA Case Cleared 12/19/2023 SPENCER WEJROWSKI
Eng Process Fee Ord 176,300 Cleared 1/3/2024 TAL SHEMEN
Green Code Cleared 1/8/2024 Hernan Arreola
DAS Clearance Cleared 1/22/2024 Hernan Arreola

Contact Information

Architect Meyer,, Mariah B; Lic. No.: C37440 8131 METCALF, SUITE 300      OVERLAND PARK, KS 66204
Contractor Savant Construction Inc; Lic. No.: 596646-B 13830 MOUNTAIN AVENUE      CHINO, CA 91710

Inspector Information

JEFFREY FULTON, (818) 374-1132 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 5/14/2024 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 5/28/2024 Approved STEVEN LEVITT
Final 6/3/2024 Not Ready for Inspection DEANDRE HOFFMAN
Green Building Final 6/3/2024 Partial Inspection DEANDRE HOFFMAN
Green Building Rough 6/3/2024 Partial Inspection DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 6/3/2024 SGSOV Not Ready DEANDRE HOFFMAN
Smoke Detectors 6/3/2024 Not Ready for Inspection DEANDRE HOFFMAN
Wood Frame 6/3/2024 Partial Inspection DEANDRE HOFFMAN
Light Gage Steel Frame 6/21/2024 Not Ready for Inspection STEVEN LEVITT
Drywall Nailing 6/24/2024 Partial Approval STEVEN LEVITT
Insulation 6/24/2024 Approved STEVEN LEVITT
Light Gage Steel Frame 6/24/2024 Approved STEVEN LEVITT
Drywall Nailing 6/26/2024 Approved STEVEN LEVITT
Insulation 6/26/2024 Partial Approval STEVEN LEVITT
Floor/Roof Diaphrgm/Shear Wall 9/25/2024 Approved STEVEN LEVITT
Structural Steel Frame 9/25/2024 Approved STEVEN LEVITT
Final 9/26/2024 Not Ready for Inspection STEVEN LEVITT
Green Building Final 9/26/2024 Approved STEVEN LEVITT
Green Building Rough 9/26/2024 Approved STEVEN LEVITT
SGSOV-Seismic Gas S/O Valve 9/26/2024 SGSOV Approved STEVEN LEVITT
Smoke Detectors 9/26/2024 Approved STEVEN LEVITT
Wood Frame 9/26/2024 Approved STEVEN LEVITT
Final 10/4/2024 Permit Finaled STEVEN LEVITT