8500 W BEVERLY BLVD # 675 90048
Certificate Information: 8500 W BEVERLY BLVD # 675 90048
- Application / Permit
- 23016-10000-21712
- Plan Check / Job No.
- B23LA12185
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- ePlan. T.I. to an existing retail space in a covered mall-beverly center.
- Permit Issued
- Issued on 8/29/2023
- Issuing Office
- Current Status
- Permit Finaled on 2/13/2024
Permit Application Status History
| Submitted | 7/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2023 | ANGELICA DAVE |
| Plan Check Approved | 7/13/2023 | ANGELICA MARTINEZ |
| Issued | 8/29/2023 | APPLICANT |
| Permit Finaled | 1/9/2024 | ALFREDO LOPEZ |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Commer,, William J; Lic. No.: NA28438 | , |
| Contractor | Horizon Retail Construction Inc; Lic. No.: 676686-B | , |
| Engineer | Sung,, Nick; Lic. No.: C49772 | 7457 BLOOMFIELD PLACE DUBLIN, OH 43016 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/11/2023 | Partial Inspection | JEROME BLACKWOOD |
| Light Gage Steel Frame | 10/19/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 10/24/2023 | Approved | JACOB MYERS |
| Drywall Nailing | 11/22/2023 | Partial Approval | RICARDO ROBLES |
| T-Bar Ceiling | 11/22/2023 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 11/27/2023 | Partial Approval | ALFREDO LOPEZ |
| T-Bar Ceiling | 11/30/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| T-Bar Ceiling | 12/11/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 1/9/2024 | Permit Finaled | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 1/9/2024 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 1/9/2024 | Approved | ALFREDO LOPEZ |