3525 W 8TH ST #G-5 90005

Certificate Information: 3525 W 8TH ST #G-5 90005

Application / Permit
23016-10000-21556
Plan Check / Job No.
B23LA12114
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Optician
Work Description
Change of Use from Retail Store to Optical Store with interior partitions, doors, T-bar ceiling, lighting fixtures, plumbing fixtures
Permit Issued
Issued on 12/8/2023
Issuing Office
Current Status
Permit Finaled on 12/5/2025
Certificate of Occupancy
TCO Issued More Information

Permit Application Status History

Submitted 6/30/2023 APPLICANT
Assigned to Plan Check Engineer 7/7/2023 ZAW HAN
Corrections Issued 7/8/2023 ZAW HAN
Applicant returned to address corrections 8/18/2023 ZAW HAN
Plan Check Approved 9/16/2023 SHANGQIN XIE
Issued 12/8/2023 APPLICANT
Permit Finaled 12/5/2025 JEFFREY FULTON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/17/2023 TERRY PHAN
Sewer availability Cleared 7/17/2023 TERRY PHAN
"D" conditions Cleared 8/21/2023 LOUIS ORTEGA
"Q" conditions Cleared 8/21/2023 LOUIS ORTEGA
"T" removal Cleared 8/21/2023 LOUIS ORTEGA
ZA Case Cleared 8/21/2023 LOUIS ORTEGA
Redevelopment Project Area Cleared 8/24/2023 SUSAN WONG

Contact Information

Architect Wu,, Juan-Lieh John; Lic. No.: C11469 412 SOUTH STONEMAN AVENUE      ALHAMBRA, CA 91801
Contractor Ym Builders Inc; Lic. No.: 1105015-B       ,

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/2/2024 Corrections Issued KATY RAMIREZ
Light Gage Steel Frame 8/12/2024 Not Ready for Inspection JEROME BLACKWOOD
Special/Order Compliance 9/16/2024 Partial Inspection JEROME BLACKWOOD
Special/Order Compliance 10/2/2024 Not Ready for Inspection JEROME BLACKWOOD
Light Gage Steel Frame 4/22/2025 Partial Approval JEROME BLACKWOOD
Drywall Nailing 5/1/2025 Approved JEROME BLACKWOOD
Final 11/13/2025 Corrections Issued JEFFREY FULTON
METHANE-Final 11/13/2025 Approved JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 11/13/2025 SGSOV Approved JEFFREY FULTON
Smoke Detectors 11/13/2025 Approved JEFFREY FULTON
Final 12/5/2025 Permit Finaled JEFFREY FULTON