3921 S 6TH AVE 90008
Certificate Information: 3921 S 6TH AVE 90008
- Application / Permit
- 23016-10000-21490
- Plan Check / Job No.
- B23LA12061
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL (E) 2-STORY SFD, ADD AND REMOVE NON STRUCTURAL WALLS, REMODEL OF KITCHEN AND BATHROOMS, EXISTING DINING AREA TO BE CONVERTED INTO BEDROOM #4 AND DEN TO BE CONVERTED INTO DINING AREA, CHANGE OF WINDOWS AND INFILL SOME. "COMPLY WITH DEPARTMENT ORDER effective date 06/09/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 7/12/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 1/30/2024
Permit Application Status History
| Submitted | 6/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2023 | MINA HABILI |
| Corrections Issued | 6/29/2023 | MINA HABILI |
| Plan Check Approved | 7/11/2023 | DANIEL SANJUAN |
| Issued | 7/12/2023 | APPLICANT |
| Permit Finaled | 1/18/2024 | WILLIAM MICHALAK |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/11/2023 | STEVE MELGAR |
| Sewer availability | Cleared | 7/11/2023 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nuno,, Arnulfo; Lic. No.: C88425 | 7057 DWIGHT WAY SAN BERNARDINO, CA 92404 |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/9/2023 | No Access for Inspection | WILLIAM MICHALAK |
| HVAC-Rough | 8/11/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| Insulation | 8/11/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| Pre-Inspection | 8/11/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 8/25/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 9/12/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| PLUMBING-Rough | 9/12/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 9/25/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| HVAC-Rough | 9/25/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| PLUMBING-Rough | 9/25/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| PLUMBING-Rough | 9/26/2023 | Corrections Issued | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 10/4/2023 | Approved | WILLIAM MICHALAK |
| HVAC-Rough | 10/4/2023 | No Access for Inspection | WILLIAM MICHALAK |
| PLUMBING-Rough | 10/4/2023 | Partial Approval | WILLIAM MICHALAK |
| Interior/Exterior Lathing | 10/19/2023 | Corrections Issued | WILLIAM MICHALAK |
| Service/Power Release | 10/19/2023 | Approved | WILLIAM MICHALAK |
| PLUMBING-Final | 12/5/2023 | Corrections Issued | WILLIAM MICHALAK |
| Final | 1/4/2024 | Corrections Issued | WILLIAM MICHALAK |
| HVAC-Final | 1/4/2024 | Corrections Issued | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 1/4/2024 | SGSOV Not Ready | WILLIAM MICHALAK |
| Smoke Detectors | 1/4/2024 | Approved | WILLIAM MICHALAK |
| Final | 1/18/2024 | Permit Finaled | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 1/18/2024 | SGSOV Approved | WILLIAM MICHALAK |