2316 W 41ST DR 90008

Certificate Information: 2316 W 41ST DR 90008

Application / Permit
23016-10000-21477
Plan Check / Job No.
B23LA12048
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan. Interior and exterior remodel to (E) 2-story SFD, scope of work to include: remodeling of existing kitchen, laundry, and upstairs bathroom, and underpinning new concrete footings
Permit Issued
Issued on 12/12/2023
Issuing Office
Current Status
Permit Finaled on 6/18/2024

Permit Application Status History

Submitted 7/2/2023 APPLICANT
Assigned to Plan Check Engineer 7/7/2023 AMY GUEVARRA
Corrections Issued 7/12/2023 AMY GUEVARRA
Plan Check Approved 8/15/2023 AMY GUEVARRA
Issued 12/12/2023 APPLICANT
Permit Finaled 6/17/2024 ANTHONY EGSON

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor C M K Construction; Lic. No.: 1066008-B       ,
Engineer Pezeshkian,, Vahik; Lic. No.: NA35278       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/5/2024 Conditional Approval ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 2/9/2024 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 2/9/2024 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 2/28/2024 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 2/28/2024 Partial Approval ANTHONY EGSON
PLUMBING-Rough 2/28/2024 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 3/1/2024 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 3/1/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 3/1/2024 Partial Approval ANTHONY EGSON
BUILDING-Rough-Frame 3/5/2024 Partial Approval ANTHONY EGSON
ELECTRICAL-Rough 3/5/2024 Partial Approval ANTHONY EGSON
PLUMBING-Rough 3/5/2024 Partial Approval ANTHONY EGSON
Drywall Nailing 3/11/2024 Partial Approval ANTHONY EGSON
BUILDING-Rough-Frame 5/7/2024 Partial Approval ANTHONY EGSON
ELECTRICAL-Rough 5/7/2024 Approved ANTHONY EGSON
HVAC-Rough 5/7/2024 Approved ANTHONY EGSON
PLUMBING-Rough 5/7/2024 Approved ANTHONY EGSON
Drywall Nailing 5/21/2024 Approved ANTHONY EGSON
ELECTRICAL-Final 6/17/2024 Approved ANTHONY EGSON
Final 6/17/2024 Permit Finaled ANTHONY EGSON
HVAC-Final 6/17/2024 Approved ANTHONY EGSON
PLUMBING-Final 6/17/2024 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 6/17/2024 SGSOV Approved ANTHONY EGSON
Smoke Detectors 6/17/2024 Approved ANTHONY EGSON