10414 S FIGUEROA ST 90003
Certificate Information: 10414 S FIGUEROA ST 90003
- Application / Permit
- 23016-10000-21415
- Plan Check / Job No.
- B23LA12009
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment Hotel
- Work Description
- FIRE DAMAGE REPAIR FOR (E) APARTMENT HOTEL. NO CHANGE TO LAYOUT NOR ADDITION. "COMPLY WITH DEPARTMENT ORDER effective date 07/28/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 4/19/2024
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 3/4/2026
Permit Application Status History
| Submitted | 6/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2023 | LAWRENCE QUIRANTE |
| Corrections Issued | 7/6/2023 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 7/12/2023 | APPLICANT |
| Plan Check Approved | 7/14/2023 | MICHAEL LANZONE |
| Issued | 4/19/2024 | APPLICANT |
| Permit Finaled | 3/4/2026 | ALFREDO LOPEZ |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/13/2024 | Approved | GABRIEL HERRERA |
| Excavation/Setback/Form/Re-Bar | 9/16/2024 | Approved | DARRYL ARNOLD |
| Wood Frame | 11/5/2024 | Corrections Issued | DARRYL ARNOLD |
| Interior/Exterior Lathing | 11/26/2024 | Corrections Issued | DARRYL ARNOLD |
| Insulation | 4/2/2025 | Partial Approval | ALFREDO LOPEZ |
| Interior/Exterior Lathing | 4/2/2025 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 4/18/2025 | Approved | DARRYL ARNOLD |
| Drywall Nailing | 5/6/2025 | Conditional Approval | DARRYL ARNOLD |
| Final | 11/19/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| Partition/T-Bar Ceiling | 11/19/2025 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 11/19/2025 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 11/19/2025 | Approved | DARRYL ARNOLD |
| Final | 2/25/2026 | Not Ready for Inspection | DARRYL ARNOLD |
| Partition/T-Bar Ceiling | 2/25/2026 | Corrections Issued | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 2/25/2026 | SGSOV Not Ready | DARRYL ARNOLD |
| Partition/T-Bar Ceiling | 2/27/2026 | Approved | ALFREDO LOPEZ |
| Final | 3/4/2026 | Permit Finaled | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/4/2026 | SGSOV Approved | ALFREDO LOPEZ |