320 S GAFFEY ST 90731

Certificate Information: 320 S GAFFEY ST 90731

Application / Permit
23016-10000-21359
Plan Check / Job No.
B23LA11975
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Coffee Shop
Work Description
Change of use from Retail to Coffee Shop. Hours of operation will be from 9:00 am to 6:00 pm.
Permit Issued
Issued on 4/9/2024
Issuing Office
San Pedro
Current Status
CofO Issued on 9/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2023 APPLICANT
Assigned to Plan Check Engineer 10/3/2023 SALVADOR QUINTANILLA
Corrections Issued 10/3/2023 SALVADOR QUINTANILLA
Applicant returned to address corrections 2/20/2024 SALVADOR QUINTANILLA
Plan Check Approved 2/20/2024 SALVADOR QUINTANILLA
No Progress 2/20/2024 SALVADOR QUINTANILLA
Plan Check Approved 3/28/2024 SALVADOR QUINTANILLA
Issued 4/9/2024 APPLICANT
Permit Finaled 9/23/2025 DAVID TSAU
CofO Issued 9/23/2025 DAVID TSAU
Permit Finaled 9/23/2025 DAVID TSAU

Permit Application Clearance Information

Food Service Establishment Cleared 2/5/2024 KENNETH BROWNE
Food establishment approval Cleared 2/20/2024 LACDHS APPROVED
Eng Process Fee Ord 176,300 Cleared 3/6/2024 JILVER MAZARIEGOS
Sewer availability Cleared 3/6/2024 JILVER MAZARIEGOS
Comm Cor/Mini-Mall Cleared 3/14/2024 CLAUDE GOODING
ZA Case Cleared 3/14/2024 CLAUDE GOODING
Redevelopment Project Area Cleared 3/21/2024 ELIZABETH GALLARDO

Contact Information

Contractor D R Construction; Lic. No.: 826773-B 727 BRIDEWELL ST      LOS ANGELES, CA 90042

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 11/7/2024 Partial Approval JOEY BUCHANAN
Wood Frame 11/14/2024 Approved JOEY BUCHANAN
Drywall Nailing 12/3/2024 Approved JOEY BUCHANAN
Final 6/13/2025 Corrections Issued MICHAEL PETRUSKO
SGSOV-Seismic Gas S/O Valve 6/13/2025 SGSOV Not Ready MICHAEL PETRUSKO
Smoke Detectors 6/13/2025 Not Ready for Inspection MICHAEL PETRUSKO
SGSOV-Seismic Gas S/O Valve 6/16/2025 SGSOV Approved MICHAEL PETRUSKO
Final 6/17/2025 Conditional Approval MICHAEL PETRUSKO
Smoke Detectors 6/17/2025 Approved MICHAEL PETRUSKO