4108 S PUNTA ALTA DR 90008
Certificate Information: 4108 S PUNTA ALTA DR 90008
- Application / Permit
- 23016-10000-21219
- Plan Check / Job No.
- B23LA11899
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan 1. RENOVATE THE KITCHEN, GREAT ROOM AND LAUNDRY ROOMS. 2. RENOVATE POWDER ROOM 3. RENOVATE EXISTING BATH ROOMS 110, AND107 4. ADD A WALK-IN CLOSET 5. VAULT CEILING AT GREAT ROOM
- Permit Issued
- Issued on 7/24/2023
- Issuing Office
- Current Status
- Permit Finaled on 8/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2023 | JOSEPH RAFOLS |
| Corrections Issued | 7/3/2023 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 7/19/2023 | JOSEPH RAFOLS |
| Plan Check Approved | 7/24/2023 | JOSEPH RAFOLS |
| Issued | 7/24/2023 | APPLICANT |
| Permit Finaled-Status Void | 7/10/2024 | ANTHONY EGSON |
| Re-Activate Permit | 8/6/2024 | ANTHONY EGSON |
| Permit Finaled | 8/6/2024 | DAVID FEILER |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/21/2023 | ROBERT HUGHES |
Contact Information
| Architect | Salcedo,, Glen Charles; Lic. No.: C33143 | P O BOX 14202 VAN NUYS, CA 91409 |
| Architect | Salcedo,, Glen Charles; Lic. No.: NA33143 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/16/2023 | Corrections Issued | ANTHONY EGSON |
| METHANE-Subgrade | 8/16/2023 | Approved | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 8/28/2023 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/28/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/2/2023 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 11/2/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 11/2/2023 | Approved | ANTHONY EGSON |
| Wood Frame | 11/2/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/14/2023 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Approved | ANTHONY EGSON |
| Shower Pan | 11/14/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/15/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2023 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 11/15/2023 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/20/2023 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2023 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 11/27/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/29/2023 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/8/2023 | Approved | BRENDAN MORELLI |
| Insulation | 12/8/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 12/8/2023 | Partial Approval | BRENDAN MORELLI |
| Drywall Nailing | 12/15/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Drywall Nailing | 12/19/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 4/12/2024 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 4/12/2024 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 5/9/2024 | Approved | ANTHONY EGSON |
| HVAC-Final | 5/9/2024 | Approved | ANTHONY EGSON |
| Final | 7/10/2024 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 7/10/2024 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 7/10/2024 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 7/10/2024 | Approved | ANTHONY EGSON |