1816 N MALTMAN AVE 90026

Certificate Information: 1816 N MALTMAN AVE 90026

Application / Permit
23016-10000-20993
Plan Check / Job No.
B23LA11773
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Interior remodel, re-framing of non load-bearing partitions, no new floor area, no exterior work, no alteration to structure. Addition of 1 full bath and 1 half bath. New plumbing tying to existing plumbing. New electrical tying to existing electrical. New mechanical bathroom ventilation. 1 new exterior window, 1 exterior window relocated. New bathroom finishes and plumbing fixtures.
Permit Issued
Issued on 7/24/2023
Issuing Office
Current Status
Permit Finaled on 1/8/2024

Permit Application Status History

Submitted 6/26/2023 APPLICANT
Assigned to Plan Check Engineer 6/27/2023 DANIEL ABRAMYAN
Corrections Issued 6/28/2023 DANIEL ABRAMYAN
Applicant returned to address corrections 7/13/2023 DANIEL YIP
Plan Check Approved 7/17/2023 KEVIN MORALES
Issued 7/24/2023 APPLICANT
Permit Finaled 1/5/2024 THOMAS LOGRASSO

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Barrett,, Henry Lucien; Lic. No.: NA39727       ,
Contractor Sjz Construction & Remodeling Inc; Lic. No.: 1094727-B       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 8/14/2023 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Rough 8/14/2023 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 8/14/2023 Not Ready for Inspection THOMAS LOGRASSO
Wood Frame 8/14/2023 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 8/16/2023 Partial Approval THOMAS LOGRASSO
HVAC-Rough 8/16/2023 Partial Approval THOMAS LOGRASSO
Insulation 8/16/2023 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 8/16/2023 Partial Approval THOMAS LOGRASSO
Wood Frame 8/16/2023 Corrections Issued THOMAS LOGRASSO
Drywall Nailing 8/24/2023 Partial Approval THOMAS LOGRASSO
Interior/Exterior Lathing 8/24/2023 Partial Approval THOMAS LOGRASSO
Shower Pan 8/24/2023 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 10/4/2023 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 10/4/2023 Approved THOMAS LOGRASSO
PLUMBING-Rough 10/4/2023 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 10/6/2023 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 10/6/2023 Approved THOMAS LOGRASSO
Drywall Nailing 10/11/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 10/11/2023 Partial Approval STUART CHAPMAN
Final 1/3/2024 Corrections Issued THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 1/3/2024 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 1/3/2024 Not Ready for Inspection THOMAS LOGRASSO
Final 1/5/2024 Permit Finaled THOMAS LOGRASSO
Smoke Detectors 1/5/2024 Approved THOMAS LOGRASSO