1816 N MALTMAN AVE 90026
Certificate Information: 1816 N MALTMAN AVE 90026
- Application / Permit
- 23016-10000-20993
- Plan Check / Job No.
- B23LA11773
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Interior remodel, re-framing of non load-bearing partitions, no new floor area, no exterior work, no alteration to structure. Addition of 1 full bath and 1 half bath. New plumbing tying to existing plumbing. New electrical tying to existing electrical. New mechanical bathroom ventilation. 1 new exterior window, 1 exterior window relocated. New bathroom finishes and plumbing fixtures.
- Permit Issued
- Issued on 7/24/2023
- Issuing Office
- Current Status
- Permit Finaled on 1/8/2024
Permit Application Status History
| Submitted | 6/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 6/28/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 7/13/2023 | DANIEL YIP |
| Plan Check Approved | 7/17/2023 | KEVIN MORALES |
| Issued | 7/24/2023 | APPLICANT |
| Permit Finaled | 1/5/2024 | THOMAS LOGRASSO |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Barrett,, Henry Lucien; Lic. No.: NA39727 | , |
| Contractor | Sjz Construction & Remodeling Inc; Lic. No.: 1094727-B | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 8/14/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 8/14/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 8/14/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Wood Frame | 8/14/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 8/16/2023 | Partial Approval | THOMAS LOGRASSO |
| HVAC-Rough | 8/16/2023 | Partial Approval | THOMAS LOGRASSO |
| Insulation | 8/16/2023 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 8/16/2023 | Partial Approval | THOMAS LOGRASSO |
| Wood Frame | 8/16/2023 | Corrections Issued | THOMAS LOGRASSO |
| Drywall Nailing | 8/24/2023 | Partial Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 8/24/2023 | Partial Approval | THOMAS LOGRASSO |
| Shower Pan | 8/24/2023 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 10/4/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 10/4/2023 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 10/4/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 10/6/2023 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 10/6/2023 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 10/11/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 10/11/2023 | Partial Approval | STUART CHAPMAN |
| Final | 1/3/2024 | Corrections Issued | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 1/3/2024 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 1/3/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 1/5/2024 | Permit Finaled | THOMAS LOGRASSO |
| Smoke Detectors | 1/5/2024 | Approved | THOMAS LOGRASSO |