853 E 106TH ST 90002

Certificate Information: 853 E 106TH ST 90002

Application / Permit
23016-10000-20757
Plan Check / Job No.
B23LA11637
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing detached carport and addition to accessory dwelling unit per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 7/11/2023
Issuing Office
Metro
Current Status
Issued on 7/11/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/23/2023 APPLICANT
Assigned to Plan Check Engineer 6/29/2023 AUNG SOE
Corrections Issued 7/4/2023 AUNG SOE
Building Plans Picked Up 7/5/2023 APPLICANT
Applicant returned to address corrections 7/10/2023 GEORGE ALVAREZ
Plan Check Approved 7/11/2023 FERNANDO FLORES
Issued 7/11/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/5/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 7/5/2023 JEANIE LAM
Sewer availability Cleared 7/5/2023 JEANIE LAM
Roof/Waste drainage to street Cleared 7/10/2023 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/1/2023 Approved JOHN KLARIN
BUILDING-Rough-Frame 11/9/2023 Corrections Issued JOHN KLARIN
PLUMBING-Rough 11/9/2023 Approved JOHN KLARIN
Footing/Foundation/Slab 11/15/2023 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 12/26/2023 Approved JOHN KLARIN
ELECTRICAL-Rough 1/29/2024 Approved JAMES CHAVEZ
HVAC-Rough 1/29/2024 Corrections Issued JAMES CHAVEZ
PLUMBING-Rough 1/29/2024 Corrections Issued JAMES CHAVEZ
HVAC-Rough 2/12/2024 Corrections Issued JAMES CHAVEZ
PLUMBING-Rough 2/12/2024 Corrections Issued JAMES CHAVEZ
BUILDING-Rough-Frame 2/20/2024 Not Ready for Inspection BEN MOLSTAD
Green Building Rough 2/20/2024 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 2/23/2024 Corrections Issued BEN MOLSTAD
Green Building Rough 2/23/2024 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Rough 2/23/2024 Corrections Issued BEN MOLSTAD
BUILDING-Rough-Frame 3/1/2024 Not Ready for Inspection BEN MOLSTAD
Green Building Rough 3/1/2024 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 3/6/2024 Approved BEN MOLSTAD
ELECTRICAL-Rough 3/6/2024 Approved BEN MOLSTAD
Green Building Rough 3/6/2024 Approved BEN MOLSTAD
HVAC-Rough 3/6/2024 Approved BEN MOLSTAD
Insulation 3/6/2024 Approved BEN MOLSTAD
PLUMBING-Rough 3/6/2024 Approved BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 3/13/2024 Corrections Issued BEN MOLSTAD
Insulation 3/13/2024 Not Ready for Inspection BEN MOLSTAD
Insulation 3/27/2024 Approved BEN MOLSTAD
Interior/Exterior Lathing 3/27/2024 Approved BEN MOLSTAD
Drywall Nailing 4/10/2024 Approved BEN MOLSTAD
Shower Pan 5/21/2024 Corrections Issued BEN MOLSTAD
Shower Pan 5/22/2024 Not Ready for Inspection BEN MOLSTAD
Shower Pan 5/24/2024 Corrections Issued BEN MOLSTAD
Shower Pan 6/7/2024 Approved JAMES CHAVEZ
Sewer 9/10/2024 Approved BARRY HACHE
Underground Mechanical 9/10/2024 Approved BARRY HACHE
ELECTRICAL-Rough 11/12/2024 Corrections Issued ANTHONY EGSON
Underground Mechanical 11/12/2024 Approved ANTHONY EGSON
ELECTRICAL-Final 11/25/2024 Corrections Issued ANTHONY EGSON
Green Building Final 11/25/2024 Not Ready for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 11/25/2024 SGSOV Not Ready ANTHONY EGSON
Smoke Detectors 11/25/2024 Not Ready for Inspection ANTHONY EGSON
Final 12/9/2024 No Access for Inspection ANTHONY EGSON
Green Building Final 12/9/2024 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 12/9/2024 SGSOV Not Ready ANTHONY EGSON
Smoke Detectors 12/9/2024 No Access for Inspection ANTHONY EGSON
Final 12/17/2024 Corrections Issued BEN MOLSTAD
Green Building Final 12/17/2024 Not Ready for Inspection BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 12/17/2024 SGSOV Not Ready BEN MOLSTAD
Smoke Detectors 12/17/2024 Not Ready for Inspection BEN MOLSTAD
Service/Power Release 4/9/2025 Not Ready for Inspection BEN MOLSTAD
Final 4/24/2025 Corrections Issued BEN MOLSTAD
Green Building Final 4/24/2025 Not Ready for Inspection BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 4/24/2025 SGSOV Not Ready BEN MOLSTAD
Smoke Detectors 4/24/2025 Not Ready for Inspection BEN MOLSTAD
Service/Power Release 5/6/2025 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 5/9/2025 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 5/13/2025 Corrections Issued ANTHONY EGSON
Final 6/4/2025 Corrections Issued ANTHONY EGSON
Green Building Final 6/4/2025 Not Ready for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 6/4/2025 SGSOV Not Ready ANTHONY EGSON
Smoke Detectors 6/4/2025 Approved ANTHONY EGSON
ELECTRICAL-Final 6/17/2025 Approved ANTHONY EGSON
Final 6/17/2025 Not Ready for Inspection ANTHONY EGSON
Green Building Final 6/17/2025 Approved ANTHONY EGSON
PLUMBING-Final 6/17/2025 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 6/17/2025 SGSOV Approved ANTHONY EGSON
Service/Power Release 6/17/2025 Approved ANTHONY EGSON
Final 6/25/2025 Conditional Approval ANTHONY EGSON
Gas Test 11/4/2025 Corrections Issued ANTHONY EGSON
Final 1/30/2026 Not Ready for Inspection ARTHUR NEGRETE
HVAC-Final 1/30/2026 Approved ARTHUR NEGRETE
Final 2/9/2026 Corrections Issued ARTHUR NEGRETE
Gas Test 2/9/2026 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 2/9/2026 SGSOV Approved ARTHUR NEGRETE