126 3/4 S BERENDO ST 90004

Certificate Information: 126 3/4 S BERENDO ST 90004

Application / Permit
23016-10000-20701
Plan Check / Job No.
B23LA11583
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: CONVERT (E) 1 STORY DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER ADM-2023-5421-ADU AND WFPP (1,200 SF max per Ordinance,LAMC 12.22 A.33 (c)-(d))
Permit Issued
Issued on 8/31/2023
Issuing Office
Current Status
CofO Issued on 4/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/23/2023 APPLICANT
Assigned to Plan Check Engineer 6/27/2023 ALEC MOUSAKHANIAN
Corrections Issued 6/28/2023 ALEC MOUSAKHANIAN
Applicant returned to address corrections 7/13/2023 KHUONG TRUONG
Applicant returned to address corrections 8/10/2023 DANIEL SMILEY
Applicant returned to address corrections 8/12/2023 AUNG SOE
Plan Check Approved 8/13/2023 AUNG SOE
Issued 8/31/2023 APPLICANT
CofO in Progress 4/2/2026 WILLIAM SIERRA
Permit Finaled 4/3/2026 DEROLD HAUFF
CofO Issued 4/3/2026 DEROLD HAUFF
Permit Finaled 4/3/2026 DEROLD HAUFF

Permit Application Clearance Information

Tenant Habitability Plan Cleared 6/29/2023 RICARDO BOHORQUEZ
Address approval Cleared 7/8/2023 JESSICA OPINION
Roof/Waste drainage to street Cleared 7/8/2023 JESSICA OPINION
Sewer availability Cleared 7/8/2023 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 7/12/2023 JESSICA OPINION
Specific Plan Cleared 8/8/2023 YAMILLET BRIZUELA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/12/2023 Corrections Issued KATHRYN BUTTERWORTH
Footing/Foundation/Slab 10/16/2023 No Access for Inspection KATHRYN BUTTERWORTH
Footing/Foundation/Slab 10/18/2023 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 10/24/2023 Corrections Issued KATHRYN BUTTERWORTH
PLUMBING-Rough 10/27/2023 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 10/31/2023 Approved JEFFREY MEAD
BUILDING-Rough-Frame 11/16/2023 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Rough 11/16/2023 Partial Approval KATHRYN BUTTERWORTH
HVAC-Rough 11/16/2023 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 11/16/2023 Approved KATHRYN BUTTERWORTH
Insulation 11/21/2023 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 11/21/2023 Partial Approval KATHRYN BUTTERWORTH
Drywall Nailing 11/30/2023 Corrections Issued RONNIE MINDANAO
Drywall Nailing 12/4/2023 Approved KATHRYN BUTTERWORTH
Shower Pan 12/7/2023 Approved CHARLES BOGHOSKHAN
ELECTRICAL-Final 1/11/2024 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Final 1/11/2024 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Final 1/11/2024 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 1/16/2024 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Final 1/23/2024 Approved SABAS ALONSO
Final 1/23/2024 Not Ready for Inspection SABAS ALONSO
Green Building Final 1/23/2024 Approved SABAS ALONSO
HVAC-Final 1/23/2024 Not Ready for Inspection SABAS ALONSO
METHANE-Final 1/23/2024 Corrections Issued SABAS ALONSO
PLUMBING-Final 1/23/2024 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 1/23/2024 SGSOV Approved SABAS ALONSO
Smoke Detectors 1/23/2024 Approved SABAS ALONSO
Final 1/30/2024 Corrections Issued RONNIE MINDANAO
METHANE-Final 1/30/2024 Not Ready for Inspection RONNIE MINDANAO
Final 2/2/2024 Partial Approval ARTHUR NEGRETE
METHANE-Final 2/2/2024 Approved ARTHUR NEGRETE
Final 4/1/2026 OK to Issue CofO WILLIAM SIERRA
Service/Power Release 4/1/2026 Approved WILLIAM SIERRA