5134 N HARTWICK ST 90041

Certificate Information: 5134 N HARTWICK ST 90041

Application / Permit
23016-10000-20677
Plan Check / Job No.
B23LA11558
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 8/24/2023
Issuing Office
Current Status
CofO Issued on 2/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2023 APPLICANT
Assigned to Plan Check Engineer 6/27/2023 PINANK PATEL
Corrections Issued 6/28/2023 PINANK PATEL
Applicant returned to address corrections 8/17/2023 DANIEL YIP
Plan Check Approved 8/22/2023 DANIEL YIP
Issued 8/24/2023 APPLICANT
CofO in Progress 2/6/2024 CRAIG VAUGHAN
Permit Finaled 2/7/2024 DEROLD HAUFF
Permit Finaled 2/7/2024 DEROLD HAUFF
CofO Issued 2/7/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/29/2023 CELINA MORENO
Sewer availability Cleared 6/29/2023 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 8/17/2023 CELINA MORENO
Grading Pre-Inspection Cleared 8/17/2023 SERGIO VALENZUELA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/3/2023 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 10/3/2023 Approved CRAIG VAUGHAN
Sewer 10/3/2023 Partial Approval CRAIG VAUGHAN
Underground Mechanical 10/3/2023 Approved CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 10/11/2023 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 10/11/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 10/31/2023 Partial Approval CRAIG VAUGHAN
HVAC-Rough 10/31/2023 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 10/31/2023 Approved CRAIG VAUGHAN
Wood Frame 10/31/2023 Approved CRAIG VAUGHAN
Insulation 11/3/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 11/3/2023 Approved CRAIG VAUGHAN
Drywall Nailing 11/9/2023 Approved CRAIG VAUGHAN
HVAC-Rough 11/9/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 11/20/2023 Approved CRAIG VAUGHAN
Shower Pan 11/20/2023 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 1/24/2024 Approved CRAIG VAUGHAN
ELECTRICAL-Final 1/24/2024 Approved CRAIG VAUGHAN
Final 1/24/2024 Corrections Issued CRAIG VAUGHAN
HVAC-Final 1/24/2024 Approved CRAIG VAUGHAN
PLUMBING-Final 1/24/2024 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 1/24/2024 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 1/24/2024 Approved CRAIG VAUGHAN
ELECTRICAL-Final 1/31/2024 Approved CRAIG VAUGHAN
Final 1/31/2024 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 1/31/2024 Approved CRAIG VAUGHAN
PLUMBING-Final 1/31/2024 Approved CRAIG VAUGHAN