656 E CRESTMOORE PL 90291

Certificate Information: 656 E CRESTMOORE PL 90291

Application / Permit
23016-10000-20650
Plan Check / Job No.
B23LA11542
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePLAN. SUPPLEMENTAL TO 17014-30000-05055. REVIEW NEW PLANS TO REVISE WORK DESCRIPTION TO REMOVE SECOND STORY ADDITION AND ROOF DECK. NEW WORK DESCRIPTION TO READ" Remodel existing one story duplex to enlarge one unit by reducing size of garage. Replace exterior finishes (doors, windows, skylights). Interior remodel to bedroom, bathroom and kitchen areas for both units. Add storage loft over kitchen area of rear unit."
Permit Issued
Issued on 10/10/2023
Issuing Office
Current Status
CofO Issued on 8/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2023 APPLICANT
Assigned to Plan Check Engineer 6/27/2023 RICARDO RAMIREZ
Corrections Issued 6/28/2023 RICARDO RAMIREZ
Applicant returned to address corrections 9/6/2023 JOE VO
Plan Check Approved 9/29/2023 KEVIN MORALES
Issued 10/10/2023 APPLICANT
CofO in Progress 8/26/2025 DAVID FEILER
Permit Finaled 8/27/2025 RICHARD STEINBACH
Permit Finaled 8/27/2025 RICHARD STEINBACH
CofO Issued 8/27/2025 RICHARD STEINBACH

Permit Application Clearance Information

Coastal Zone Cleared 9/19/2023 DANIEL CORONADO
ZA Case Cleared 9/19/2023 DANIEL CORONADO
Specific Plan Cleared 9/27/2023 LUIS LOPEZ
ZI Cleared 9/27/2023 LUIS LOPEZ

Contact Information

Architect Lelieur,, Scott Kendall; Lic. No.: C24145 3502 LAKELAND DR.      AUSTIN, TX 78731
Contractor Big & Tall Construction Inc; Lic. No.: 703267-B 5364 N STERLING CENTER DRIVE      WESTLAKE VILLAGE, CA 91361
Engineer Yamini,, Soly; Lic. No.: C33719 540 WARNER AVE      LOS ANGELES, CA 90024

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/14/2024 Partial Inspection HERBERT GIRON
Excavation/Setback/Form/Re-Bar 3/5/2024 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/8/2024 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 5/2/2024 Not Ready for Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 5/14/2024 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 5/14/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/4/2024 Partial Inspection DAVID FEILER
Final 8/26/2025 OK to Issue CofO DAVID FEILER
SGSOV-Seismic Gas S/O Valve 8/26/2025 SGSOV Approved DAVID FEILER
Smoke Detectors 8/26/2025 Approved DAVID FEILER
Wood Frame 8/26/2025 Approved DAVID FEILER