401-401 1/2 E 109TH ST 90061
Certificate Information: 401-401 1/2 E 109TH ST 90061
- Application / Permit
- 23016-10000-20617
- Plan Check / Job No.
- B23LA11519
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT EXISTING GARAGE INTO ADU 366 SQ FT AND CONVERT PORTION OF THE EXISTING UNIT A 594 SQ FT INTO PROPOSED ATTACHED ADU PER ORDIANANCE AND LAMC 12.22A33(c)&(e). TOTAL ADU = 960 SQ FT NEW GABLE ROOF OVER EXISTING BUILDING.
- Permit Issued
- Issued on 11/22/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2023 | ZAW HAN |
| Corrections Issued | 7/3/2023 | ZAW HAN |
| Building Plans Picked Up | 7/5/2023 | APPLICANT |
| Applicant returned to address corrections | 3/1/2024 | NEHEMIAS RAMOS |
| Plan Check Approved | 3/6/2024 | JOSE VELAZQUEZ |
| Issued | 11/22/2024 | APPLICANT |
| CofO in Progress | 2/24/2026 | ARTHUR NEGRETE |
| Permit Finaled | 6/5/2026 | ANSON MAGLASANG |
| CofO Issued | 6/5/2026 | ANSON MAGLASANG |
| Permit Finaled | 6/5/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 1/10/2024 | DAVID VO |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2024 | DAVID VO |
| Highway dedication | Cleared | 1/10/2024 | DAVID VO |
| Roof/Waste drainage to street | Cleared | 1/10/2024 | DAVID VO |
| Sewer availability | Cleared | 1/10/2024 | DAVID VO |
| ZA Case | Cleared | 1/10/2024 | RYAN LY |
| Public Works-Highway Ded. | Cleared | 1/10/2024 | DAVID VO |
| Public Works-Sewers | Cleared | 1/10/2024 | DAVID VO |
| Hold | Cleared | 12/23/2024 | ALEXIS SCHULTZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chen,, Yeshen Jason; Lic. No.: C40169 | 20601 ALDA CT WALNUT, CA 91789 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2024 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 12/24/2024 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2024 | Not Ready for Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 1/2/2025 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 1/2/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Footing/Foundation/Slab | 1/6/2025 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 1/6/2025 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 1/8/2025 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 1/8/2025 | Partial Approval | BEN MOLSTAD |
| Footing/Foundation/Slab | 1/10/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 2/14/2025 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 2/14/2025 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 2/14/2025 | Approved | JOSEPH MCGARRY |
| Wood Frame | 2/14/2025 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 5/22/2025 | No Access for Inspection | JOHN KLARIN |
| Insulation | 5/30/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Interior/Exterior Lathing | 5/30/2025 | Corrections Issued | BEN MOLSTAD |
| Insulation | 6/27/2025 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 6/27/2025 | Approved | JOHN KLARIN |
| Insulation | 7/10/2025 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 7/21/2025 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 1/6/2026 | Approved | ARTHUR NEGRETE |
| Final | 1/6/2026 | Corrections Issued | ARTHUR NEGRETE |
| Rough-Elec/Plmb/HVAC | 1/6/2026 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 1/6/2026 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 1/6/2026 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 1/12/2026 | Approved | ARTHUR NEGRETE |
| Final | 1/12/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| HVAC-Final | 1/12/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 1/12/2026 | Approved | ARTHUR NEGRETE |
| Final | 2/23/2026 | OK to Issue CofO | ARTHUR NEGRETE |
| Service/Power Release | 3/5/2026 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 3/26/2026 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 3/27/2026 | Approved | ANSON MAGLASANG |