1353 N CORONADO ST 90026
Certificate Information: 1353 N CORONADO ST 90026
- Application / Permit
- 23016-10000-20542
- Plan Check / Job No.
- B23LA11467
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 1/11/2024
- Issuing Office
- Current Status
- CofO Issued on 6/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 6/28/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 10/18/2023 | ALEC MOUSAKHANIAN |
| Issued | 1/11/2024 | APPLICANT |
| CofO in Progress | 6/17/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 6/22/2025 | DEROLD HAUFF |
| CofO Issued | 6/22/2025 | DEROLD HAUFF |
| Permit Finaled | 6/22/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/14/2023 | NEIL TUANO |
| Roof/Waste drainage to street | Cleared | 7/14/2023 | NEIL TUANO |
| Sewer availability | Cleared | 7/14/2023 | NEIL TUANO |
| Eng Process Fee Ord 176,300 | Cleared | 7/17/2023 | NEIL TUANO |
| Grading Pre-Inspection | Cleared | 7/31/2023 | SERGIO VALENZUELA |
| Construction near power lines | Cleared | 10/16/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/16/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Greco,, Adam M; Lic. No.: NA4077 | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/17/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 6/10/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 6/21/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/2/2024 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 8/12/2024 | Corrections Issued | BRENDAN MORELLI |
| Interior/Exterior Lathing | 8/21/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Underground Mechanical | 8/21/2024 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 9/6/2024 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2024 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 9/25/2024 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 10/25/2024 | Approved | LUIS CASTRO |
| Shower Pan | 10/25/2024 | Approved | LUIS CASTRO |
| HVAC-Rough | 10/28/2024 | Approved | JOHN QUINTANILLA |
| Wood Frame | 10/28/2024 | Approved | JOHN QUINTANILLA |
| Insulation | 11/1/2024 | Approved | LUIS CASTRO |
| Drywall Nailing | 11/14/2024 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 11/14/2024 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/14/2025 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 4/14/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 4/14/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Final | 4/14/2025 | Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 4/14/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 5/20/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Final | 5/20/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 6/11/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Final | 6/17/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |