7249 S MCCOOL AVE 90045
Certificate Information: 7249 S MCCOOL AVE 90045
- Application / Permit
- 23016-10000-20418
- Plan Check / Job No.
- B23LA11382
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Convert (E) Detached garage into an ADU. Per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 1/16/2024
- Issuing Office
- Current Status
- CofO Issued on 7/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2023 | ALFREDO JARA |
| Corrections Issued | 6/27/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 12/8/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 12/22/2023 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 12/29/2023 | DAVID CASTILLO |
| Plan Check Approved | 1/11/2024 | JOHNPAUL ISIP |
| Issued | 1/16/2024 | APPLICANT |
| CofO in Progress | 7/25/2024 | TEMISTOCLES CAAL |
| Permit Finaled | 7/26/2024 | DANIEL ORRANTE |
| CofO Issued | 7/26/2024 | DANIEL ORRANTE |
| Permit Finaled | 7/26/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 8/15/2023 | ROBERT SANCHEZ |
| Address approval | Cleared | 8/17/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2023 | JASON NG |
| Roof/Waste drainage to street | Cleared | 8/17/2023 | JASON NG |
| Sewer availability | Cleared | 8/17/2023 | JASON NG |
| Construction near power lines | Cleared | 11/29/2023 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 12/8/2023 | ALFREDO JARA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/1/2024 | Partial Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 3/27/2024 | Partial Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 3/27/2024 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 4/2/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 4/15/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 5/9/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 5/9/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 5/9/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 5/9/2024 | Partial Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 5/9/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 5/14/2024 | Partial Approval | TEMISTOCLES CAAL |
| Insulation | 5/14/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 5/17/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 5/17/2024 | Approved | TEMISTOCLES CAAL |
| Gas Test | 6/3/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 6/3/2024 | Partial Approval | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 6/7/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 7/12/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 7/12/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 7/12/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 7/12/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 7/12/2024 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/12/2024 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 7/12/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 7/24/2024 | Approved | TEMISTOCLES CAAL |
| Final | 7/24/2024 | OK to Issue CofO | TEMISTOCLES CAAL |
| HVAC-Final | 7/24/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 7/24/2024 | Approved | TEMISTOCLES CAAL |