7427 W 88TH PL 90045

Certificate Information: 7427 W 88TH PL 90045

Application / Permit
23016-10000-20216
Plan Check / Job No.
B23LA11278
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan Convert (E) attached garage in (E) SFD to an Accessory Dwelling Unit per Ordinance.
Permit Issued
Issued on 11/7/2023
Issuing Office
Current Status
CofO Issued on 6/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/30/2023 APPLICANT
Assigned to Plan Check Engineer 7/7/2023 AMY GUEVARRA
Corrections Issued 7/12/2023 AMY GUEVARRA
Applicant returned to address corrections 8/4/2023 JOHNPAUL ISIP
Plan Check Approved 8/30/2023 FARSHAD ALIMOHAMADI
Issued 11/7/2023 APPLICANT
CofO in Progress 5/31/2024 BOBBY KEY
Permit Finaled 6/3/2024 DANIEL ORRANTE
CofO Issued 6/3/2024 DANIEL ORRANTE
Permit Finaled 6/3/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/17/2023 AHMED AMARRAGY
Roof/Waste drainage to street Cleared 7/17/2023 AHMED AMARRAGY
Sewer availability Cleared 7/17/2023 AHMED AMARRAGY
Grading Pre-Inspection Cleared 7/26/2023 ROBERT HUGHES
Specific Plan Cleared 8/4/2023 PEDRO AYALA
ZA Case Cleared 8/8/2023 MAXFIELD VERMY
Eng Process Fee Ord 176,300 Cleared 8/28/2023 KIMBERLY HERNANDEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/20/2023 Conditional Approval BOBBY KEY
Footing/Foundation/Slab 11/28/2023 Approved BOBBY KEY
PLUMBING-Rough 11/28/2023 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 1/23/2024 Partial Approval BOBBY KEY
Rough-Elec/Plmb/HVAC 1/23/2024 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 1/31/2024 Conditional Approval BOBBY KEY
ELECTRICAL-Rough 1/31/2024 Approved BOBBY KEY
Interior/Exterior Lathing 1/31/2024 Partial Approval BOBBY KEY
Insulation 2/6/2024 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 2/15/2024 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 2/15/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 2/22/2024 Approved BOBBY KEY
Green Building Rough 2/22/2024 Approved BOBBY KEY
Drywall Nailing 2/28/2024 Approved BOBBY KEY
ELECTRICAL-Final 2/28/2024 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 5/20/2024 SGSOV Not Ready BOBBY KEY
ELECTRICAL-Final 5/31/2024 Approved BOBBY KEY
Final 5/31/2024 OK to Issue CofO BOBBY KEY
HVAC-Final 5/31/2024 Approved BOBBY KEY
PLUMBING-Final 5/31/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 5/31/2024 SGSOV Approved BOBBY KEY
Smoke Detectors 5/31/2024 Approved BOBBY KEY