1112 1/2 E LANZIT AVE 90059
Certificate Information: 1112 1/2 E LANZIT AVE 90059
- Application / Permit
- 23016-10000-20169
- Plan Check / Job No.
- B23LA11273
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan: Proposed Garage Conversion to ADU per GCS 65852.2(e)(1)(d) and LAMC 12.22 A.33(c)(d) and (g)
- Permit Issued
- Issued on 8/18/2023
- Issuing Office
- Current Status
- CofO Issued on 8/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2023 | JOHNPAUL ISIP |
| Corrections Issued | 6/26/2023 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 8/10/2023 | DAVID CASTILLO |
| Plan Check Approved | 8/16/2023 | DAVID CASTILLO |
| Issued | 8/18/2023 | APPLICANT |
| CofO in Progress | 8/15/2024 | BEN MOLSTAD |
| Permit Finaled | 8/15/2024 | ANSON MAGLASANG |
| CofO Issued | 8/15/2024 | ANSON MAGLASANG |
| Permit Finaled | 8/15/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 7/14/2023 | ANA SORIANO |
| Sewer availability | Cleared | 7/14/2023 | ANA SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2023 | ANA SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/11/2023 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Rough | 12/13/2023 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 12/20/2023 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 12/20/2023 | Approved | JOHN KLARIN |
| Green Building Rough | 12/20/2023 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 12/27/2023 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 12/27/2023 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 12/27/2023 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 1/10/2024 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 1/10/2024 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 1/10/2024 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 1/10/2024 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 1/25/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 1/25/2024 | Approved | JAMES CHAVEZ |
| Green Building Rough | 1/25/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| PLUMBING-Rough | 1/25/2024 | Corrections Issued | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 2/2/2024 | Partial Approval | JOHN KLARIN |
| ELECTRICAL-Rough | 2/2/2024 | Corrections Issued | JOHN KLARIN |
| Green Building Rough | 2/2/2024 | Not Ready for Inspection | JOHN KLARIN |
| HVAC-Rough | 2/2/2024 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Rough | 2/2/2024 | Partial Approval | JOHN KLARIN |
| Insulation | 2/6/2024 | Approved | JAMES CHAVEZ |
| Pre-Inspection | 2/6/2024 | Partial Inspection | JAMES CHAVEZ |
| Drywall Nailing | 2/15/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Rough | 2/15/2024 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 2/20/2024 | Approved | BEN MOLSTAD |
| Drywall Nailing | 2/20/2024 | Approved | BEN MOLSTAD |
| Green Building Rough | 2/20/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 6/18/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 6/18/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Gas Test | 6/18/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Final | 6/18/2024 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Rough | 6/18/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 6/18/2024 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 6/18/2024 | SGSOV Not Ready | BEN MOLSTAD |
| Smoke Detectors | 6/18/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 7/3/2024 | Approved | JAMES CHAVEZ |
| Final | 7/3/2024 | Corrections Issued | JAMES CHAVEZ |
| Gas Test | 7/3/2024 | Approved | JAMES CHAVEZ |
| Green Building Final | 7/3/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 7/3/2024 | SGSOV Not Ready | JAMES CHAVEZ |
| Smoke Detectors | 7/3/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Final | 7/18/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 7/18/2024 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 7/18/2024 | SGSOV Not Ready | BEN MOLSTAD |
| Smoke Detectors | 7/18/2024 | Approved | BEN MOLSTAD |
| Final | 7/23/2024 | Corrections Issued | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 7/23/2024 | SGSOV Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 8/6/2024 | Approved | BEN MOLSTAD |
| Final | 8/6/2024 | Corrections Issued | BEN MOLSTAD |
| HVAC-Final | 8/6/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 8/6/2024 | Approved | BEN MOLSTAD |
| Final | 8/14/2024 | OK to Issue CofO | BEN MOLSTAD |