1112 1/2 E LANZIT AVE 90059

Certificate Information: 1112 1/2 E LANZIT AVE 90059

Application / Permit
23016-10000-20169
Plan Check / Job No.
B23LA11273
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan: Proposed Garage Conversion to ADU per GCS 65852.2(e)(1)(d) and LAMC 12.22 A.33(c)(d) and (g)
Permit Issued
Issued on 8/18/2023
Issuing Office
Current Status
CofO Issued on 8/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2023 APPLICANT
Assigned to Plan Check Engineer 6/23/2023 JOHNPAUL ISIP
Corrections Issued 6/26/2023 JOHNPAUL ISIP
Applicant returned to address corrections 8/10/2023 DAVID CASTILLO
Plan Check Approved 8/16/2023 DAVID CASTILLO
Issued 8/18/2023 APPLICANT
CofO in Progress 8/15/2024 BEN MOLSTAD
Permit Finaled 8/15/2024 ANSON MAGLASANG
CofO Issued 8/15/2024 ANSON MAGLASANG
Permit Finaled 8/15/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 7/14/2023 ANA SORIANO
Sewer availability Cleared 7/14/2023 ANA SORIANO
Eng Process Fee Ord 176,300 Cleared 8/3/2023 ANA SORIANO

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/11/2023 Corrections Issued JOHN KLARIN
PLUMBING-Rough 12/13/2023 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 12/20/2023 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 12/20/2023 Approved JOHN KLARIN
Green Building Rough 12/20/2023 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 12/27/2023 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 12/27/2023 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 12/27/2023 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 1/10/2024 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 1/10/2024 Not Ready for Inspection JOHN KLARIN
Green Building Rough 1/10/2024 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 1/10/2024 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 1/25/2024 Not Ready for Inspection JAMES CHAVEZ
ELECTRICAL-Rough 1/25/2024 Approved JAMES CHAVEZ
Green Building Rough 1/25/2024 Not Ready for Inspection JAMES CHAVEZ
PLUMBING-Rough 1/25/2024 Corrections Issued JAMES CHAVEZ
BUILDING-Rough-Frame 2/2/2024 Partial Approval JOHN KLARIN
ELECTRICAL-Rough 2/2/2024 Corrections Issued JOHN KLARIN
Green Building Rough 2/2/2024 Not Ready for Inspection JOHN KLARIN
HVAC-Rough 2/2/2024 Corrections Issued JOHN KLARIN
PLUMBING-Rough 2/2/2024 Partial Approval JOHN KLARIN
Insulation 2/6/2024 Approved JAMES CHAVEZ
Pre-Inspection 2/6/2024 Partial Inspection JAMES CHAVEZ
Drywall Nailing 2/15/2024 Not Ready for Inspection BEN MOLSTAD
Green Building Rough 2/15/2024 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 2/20/2024 Approved BEN MOLSTAD
Drywall Nailing 2/20/2024 Approved BEN MOLSTAD
Green Building Rough 2/20/2024 Approved BEN MOLSTAD
ELECTRICAL-Rough 6/18/2024 Not Ready for Inspection BEN MOLSTAD
Final 6/18/2024 Not Ready for Inspection BEN MOLSTAD
Gas Test 6/18/2024 Not Ready for Inspection BEN MOLSTAD
Green Building Final 6/18/2024 Not Ready for Inspection BEN MOLSTAD
HVAC-Rough 6/18/2024 Approved BEN MOLSTAD
PLUMBING-Rough 6/18/2024 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 6/18/2024 SGSOV Not Ready BEN MOLSTAD
Smoke Detectors 6/18/2024 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 7/3/2024 Approved JAMES CHAVEZ
Final 7/3/2024 Corrections Issued JAMES CHAVEZ
Gas Test 7/3/2024 Approved JAMES CHAVEZ
Green Building Final 7/3/2024 Not Ready for Inspection JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 7/3/2024 SGSOV Not Ready JAMES CHAVEZ
Smoke Detectors 7/3/2024 Not Ready for Inspection JAMES CHAVEZ
Final 7/18/2024 Corrections Issued BEN MOLSTAD
Green Building Final 7/18/2024 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 7/18/2024 SGSOV Not Ready BEN MOLSTAD
Smoke Detectors 7/18/2024 Approved BEN MOLSTAD
Final 7/23/2024 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 7/23/2024 SGSOV Approved BEN MOLSTAD
ELECTRICAL-Final 8/6/2024 Approved BEN MOLSTAD
Final 8/6/2024 Corrections Issued BEN MOLSTAD
HVAC-Final 8/6/2024 Approved BEN MOLSTAD
PLUMBING-Final 8/6/2024 Approved BEN MOLSTAD
Final 8/14/2024 OK to Issue CofO BEN MOLSTAD