6867 W IRIS CIR 90068

Certificate Information: 6867 W IRIS CIR 90068

Application / Permit
23016-10000-19843
Plan Check / Job No.
B23LA11102
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan REBUILD WATER DAMAGED EXTERIOR WALL REMODEL PRIMARY BATH- REMODEL 2 BATHROOMS- INTERIOR ONLY No change in RFA, dimensions, height of structure or setbacks.
Permit Issued
Issued on 9/15/2023
Issuing Office
Current Status
Issued on 4/30/2024

Permit Application Status History

Submitted 6/15/2023 APPLICANT
Assigned to Plan Check Engineer 6/22/2023 JAD BASMA
Corrections Issued 6/25/2023 JAD BASMA
Quality Review Completed 7/5/2023 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 9/8/2023 JAD BASMA
Issued 9/15/2023 APPLICANT
Refund in Progress 4/3/2024 SELENIA GARCIA
Refund Denied 4/30/2024 EMILY HU
Issued 4/30/2024 EMILY HU

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/12/2023 SERGIO VALENZUELA
Roof/Waste drainage to street Cleared 7/27/2023 TREVOR QUAN
Sewer availability Cleared 7/27/2023 TREVOR QUAN
CPC Cleared 7/28/2023 MAYELA VILLA
Eng Process Fee Ord 176,300 Cleared 7/31/2023 TREVOR QUAN
HPOZ Cleared 8/28/2023 MICAELA TORRES-GIL

Contact Information

Architect Duffy,, Robert K; Lic. No.: NA7604       ,
Contractor Wolf Pack Professional Builders Inc; Lic. No.: 1031553-B       ,

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/3/2024 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 1/11/2024 Corrections Issued STUART CHAPMAN
Deputy Drilled-In Anchors 1/19/2024 Conditional Approval BRIAN SULLIVAN
Wood Frame 2/21/2024 Not Ready for Inspection ROY SPAULDING
Wood Frame 5/2/2024 Not Ready for Inspection ROY SPAULDING
Interior/Exterior Lathing 3/5/2025 Not Ready for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 3/7/2025 Approved CRAIG VAUGHAN
Wood Frame 3/7/2025 Corrections Issued CRAIG VAUGHAN
Wood Frame 3/27/2025 Corrections Issued CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/8/2025 Partial Approval CRAIG VAUGHAN
Drywall Nailing 5/5/2025 Partial Approval CRAIG VAUGHAN
Wood Frame 11/6/2025 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 1/21/2026 Partial Approval CRAIG VAUGHAN
Insulation 4/15/2026 Approved CRAIG VAUGHAN
Drywall Nailing 4/21/2026 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 4/21/2026 Approved CRAIG VAUGHAN