6221 S MADDEN AVE 90043

Certificate Information: 6221 S MADDEN AVE 90043

Application / Permit
23016-10000-19830
Plan Check / Job No.
B23LA11089
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED 18'-5" X 18'-2" GARAGE INTO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A) - PER ENGINEER
Permit Issued
Issued on 6/25/2024
Issuing Office
Current Status
CofO Issued on 2/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2023 APPLICANT
Assigned to Plan Check Engineer 6/23/2023 DANIEL ABRAMYAN
Corrections Issued 6/26/2023 DANIEL ABRAMYAN
Applicant returned to address corrections 9/20/2023 KAMYAR EMAMI
Applicant returned to address corrections 10/4/2023 MIROOSH KHACHATOORIAN
Plan Check Approved 10/20/2023 MIROOSH KHACHATOORIAN
Issued 6/25/2024 APPLICANT
CofO in Progress 2/27/2026 SALVADOR MARTINEZ
Permit Finaled 2/27/2026 DEROLD HAUFF
CofO Issued 2/27/2026 DEROLD HAUFF
Permit Finaled 2/27/2026 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 7/27/2023 NEIL TUANO
Address approval Cleared 7/28/2023 NEIL TUANO
Eng Process Fee Ord 176,300 Cleared 7/28/2023 NEIL TUANO
Construction near power lines Cleared 8/26/2023 TINA MIRANDA

Contact Information

Contractor Artisan & Co; Lic. No.: 1115180-B       ,
Engineer Gorgy,, Moheb Shohdy; Lic. No.: C53260 1545 VICTORY BLVD STE 102      GLENDALE, CA 91201

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/12/2024 Corrections Issued JOSE MACIAS
PLUMBING-Rough 7/12/2024 Not Ready for Inspection JOSE MACIAS
Pre-Inspection 7/12/2024 Corrections Issued JOSE MACIAS
Underground Mechanical 7/29/2024 Corrections Issued JOSE MACIAS
Sewer 8/6/2024 Approved JOSE MACIAS
Underground Mechanical 8/6/2024 Approved JOSE MACIAS
Underground Mechanical 8/22/2024 Approved JOSE MACIAS
Pre-Inspection 9/13/2024 Partial Inspection JOHN QUINTANILLA
BUILDING-Rough-Frame 9/23/2024 Not Ready for Inspection AMIR NAZARIAN
ELECTRICAL-Rough 9/23/2024 Corrections Issued AMIR NAZARIAN
PLUMBING-Rough 9/23/2024 Corrections Issued AMIR NAZARIAN
Footing/Foundation/Slab 9/25/2024 Approved JOSE MACIAS
BUILDING-Rough-Frame 10/7/2024 Corrections Issued AMIR NAZARIAN
ELECTRICAL-Rough 10/7/2024 Approved AMIR NAZARIAN
HVAC-Rough 10/7/2024 Corrections Issued AMIR NAZARIAN
Interior/Exterior Lathing 10/7/2024 Corrections Issued AMIR NAZARIAN
PLUMBING-Rough 10/7/2024 Approved AMIR NAZARIAN
BUILDING-Rough-Frame 10/31/2024 Corrections Issued AMIR NAZARIAN
HVAC-Rough 10/31/2024 Approved AMIR NAZARIAN
Interior/Exterior Lathing 10/31/2024 Corrections Issued AMIR NAZARIAN
Shower Pan 10/31/2024 Approved AMIR NAZARIAN
Interior/Exterior Lathing 11/21/2024 Partial Approval ALEX COLIN
Interior/Exterior Lathing 11/22/2024 Partial Approval ALEX COLIN
Insulation 11/27/2024 Corrections Issued AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 1/23/2025 Corrections Issued JOHN QUINTANILLA
Wood Frame 1/23/2025 Corrections Issued JOHN QUINTANILLA
Drywall Nailing 2/6/2025 Partial Approval JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 2/6/2025 Not Ready for Inspection JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 3/11/2025 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 12/12/2025 Approved SALVADOR MARTINEZ
Drywall Nailing 12/12/2025 Approved SALVADOR MARTINEZ
Final 12/12/2025 OK to Issue CofO SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 12/12/2025 SGSOV Approved SALVADOR MARTINEZ
Smoke Detectors 12/12/2025 Approved SALVADOR MARTINEZ