5812 W PICKFORD ST 90035

Certificate Information: 5812 W PICKFORD ST 90035

Application / Permit
23016-10000-19822
Plan Check / Job No.
B23LA11085
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
**eplan** Covert existing detached garage and second story recreation room to ADU per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 7/27/2023
Issuing Office
Current Status
CofO Issued on 12/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2023 APPLICANT
Assigned to Plan Check Engineer 6/23/2023 EDWIN ESPIN
Corrections Issued 6/26/2023 EDWIN ESPIN
Applicant returned to address corrections 7/17/2023 EDWIN ESPIN
Plan Check Approved 7/24/2023 EDWIN ESPIN
Issued 7/27/2023 APPLICANT
CofO in Progress 12/11/2024 ARTHUR NEGRETE
Permit Finaled 12/29/2024 DEROLD HAUFF
CofO Issued 12/29/2024 DEROLD HAUFF
Permit Finaled 12/29/2024 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 7/5/2023 NEIL TUANO
Address approval Cleared 7/8/2023 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 7/14/2023 NEIL TUANO
Tenant Habitability Plan Cleared 7/17/2023 RICARDO BOHORQUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/4/2023 Partial Inspection LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 8/11/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 8/17/2023 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 8/17/2023 Approved JOSE AVILA
ELECTRICAL-Rough 11/28/2023 Approved ALIZAH MAYAGOITIA
HVAC-Rough 12/8/2023 Corrections Issued RONNIE MINDANAO
PLUMBING-Rough 12/8/2023 Corrections Issued RONNIE MINDANAO
BUILDING-Rough-Frame 3/22/2024 Partial Approval STUART CHAPMAN
Green Building Rough 3/22/2024 Approved STUART CHAPMAN
HVAC-Final 3/22/2024 Corrections Issued STUART CHAPMAN
HVAC-Rough 3/22/2024 Approved STUART CHAPMAN
Insulation 3/22/2024 Approved STUART CHAPMAN
METHANE-Rough 3/22/2024 Approved STUART CHAPMAN
PLUMBING-Final 3/22/2024 Corrections Issued STUART CHAPMAN
PLUMBING-Rough 3/22/2024 Partial Approval STUART CHAPMAN
PLUMBING-Final 4/4/2024 Corrections Issued RICHARD DOCKUS
PLUMBING-Final 4/29/2024 Approved ALIZAH MAYAGOITIA
HVAC-Final 11/25/2024 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 12/2/2024 Approved JOSE MACIAS
Final 12/2/2024 Corrections Issued JOSE MACIAS
Green Building Final 12/2/2024 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 12/2/2024 SGSOV Approved JOSE MACIAS
Smoke Detectors 12/2/2024 Approved JOSE MACIAS
Final 12/5/2024 Not Ready for Inspection ARTHUR NEGRETE
ELECTRICAL-Final 12/9/2024 Approved ARTHUR NEGRETE
Final 12/9/2024 OK to Issue CofO ARTHUR NEGRETE