5812 W PICKFORD ST 90035
Certificate Information: 5812 W PICKFORD ST 90035
- Application / Permit
- 23016-10000-19822
- Plan Check / Job No.
- B23LA11085
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- **eplan** Covert existing detached garage and second story recreation room to ADU per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 7/27/2023
- Issuing Office
- Current Status
- CofO Issued on 12/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2023 | EDWIN ESPIN |
| Corrections Issued | 6/26/2023 | EDWIN ESPIN |
| Applicant returned to address corrections | 7/17/2023 | EDWIN ESPIN |
| Plan Check Approved | 7/24/2023 | EDWIN ESPIN |
| Issued | 7/27/2023 | APPLICANT |
| CofO in Progress | 12/11/2024 | ARTHUR NEGRETE |
| Permit Finaled | 12/29/2024 | DEROLD HAUFF |
| CofO Issued | 12/29/2024 | DEROLD HAUFF |
| Permit Finaled | 12/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 7/5/2023 | NEIL TUANO |
| Address approval | Cleared | 7/8/2023 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2023 | NEIL TUANO |
| Tenant Habitability Plan | Cleared | 7/17/2023 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/4/2023 | Partial Inspection | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 8/11/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 8/17/2023 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 8/17/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 11/28/2023 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 12/8/2023 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Rough | 12/8/2023 | Corrections Issued | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 3/22/2024 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 3/22/2024 | Approved | STUART CHAPMAN |
| HVAC-Final | 3/22/2024 | Corrections Issued | STUART CHAPMAN |
| HVAC-Rough | 3/22/2024 | Approved | STUART CHAPMAN |
| Insulation | 3/22/2024 | Approved | STUART CHAPMAN |
| METHANE-Rough | 3/22/2024 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 3/22/2024 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 3/22/2024 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Final | 4/4/2024 | Corrections Issued | RICHARD DOCKUS |
| PLUMBING-Final | 4/29/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 11/25/2024 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 12/2/2024 | Approved | JOSE MACIAS |
| Final | 12/2/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 12/2/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 12/2/2024 | SGSOV Approved | JOSE MACIAS |
| Smoke Detectors | 12/2/2024 | Approved | JOSE MACIAS |
| Final | 12/5/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| ELECTRICAL-Final | 12/9/2024 | Approved | ARTHUR NEGRETE |
| Final | 12/9/2024 | OK to Issue CofO | ARTHUR NEGRETE |