1339 N MARINETTE ROAD 90272

Certificate Information: 1339 N MARINETTE ROAD 90272

Application / Permit
23016-10000-19787
Plan Check / Job No.
B23LA11068
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Exterior and Interior Remodel to (E) 1-story SFD per engineer details. Scope to include Addition by Roof Enclosure of 21.5 SF and Remove-and-Rebuild 78 SF
Permit Issued
Issued on 7/7/2023
Issuing Office
Metro
Current Status
CofO Issued on 5/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2023 APPLICANT
Assigned to Plan Check Engineer 6/23/2023 MICHAEL LANZONE
Corrections Issued 6/26/2023 MICHAEL LANZONE
Building Plans Picked Up 6/27/2023 APPLICANT
Plan Check Approved 7/7/2023 VICTOR CHEN
Issued 7/7/2023 APPLICANT
CofO in Progress 4/26/2024 ARAM AVEDISIAN
Permit Finaled 5/4/2024 DANIEL ORRANTE
CofO Issued 5/4/2024 DANIEL ORRANTE
Permit Finaled 5/4/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/3/2023 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 7/3/2023 HISASHI KOBAYAKAWA
Sewer availability Cleared 7/3/2023 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 7/7/2023 MICHAEL LANZONE

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari,, Arthur; Lic. No.: C53497 PO BOX 7112      NORTHRIDGE, CA 91327

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/28/2023 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 9/18/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Sewer 9/18/2023 Approved OGANES TARAKHCHYAN
Underground Mechanical 9/18/2023 Corrections Issued OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 9/20/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 9/25/2023 Partial Approval OGANES TARAKHCHYAN
Underground Mechanical 9/25/2023 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 11/16/2023 Approved ARAM AVEDISIAN
HVAC-Rough 11/16/2023 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 11/22/2023 Approved ARAM AVEDISIAN
HVAC-Rough 11/22/2023 Approved ARAM AVEDISIAN
PLUMBING-Rough 11/22/2023 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 11/28/2023 Approved ARAM AVEDISIAN
Gas Test 11/28/2023 Partial Approval ARAM AVEDISIAN
Insulation 12/15/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 12/15/2023 Partial Approval ARAM AVEDISIAN
Shower Pan 12/15/2023 Approved ARAM AVEDISIAN
Drywall Nailing 12/20/2023 Approved EVAN COOPER
Interior/Exterior Lathing 12/22/2023 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Final 4/17/2024 Approved ARAM AVEDISIAN
HVAC-Final 4/17/2024 Approved ARAM AVEDISIAN
Final 4/24/2024 Corrections Issued MEL KHACHATOURIAN
Footing/Foundation/Slab 4/24/2024 Approved MEL KHACHATOURIAN
PLUMBING-Final 4/24/2024 Not Ready for Inspection MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 4/24/2024 SGSOV Not Ready MEL KHACHATOURIAN
Smoke Detectors 4/24/2024 Approved MEL KHACHATOURIAN
Final 4/26/2024 OK to Issue CofO ARAM AVEDISIAN
Gas Test 4/26/2024 Approved ARAM AVEDISIAN
PLUMBING-Final 4/26/2024 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 4/26/2024 SGSOV Approved ARAM AVEDISIAN