22002 W YBARRA ROAD 91364
Certificate Information: 22002 W YBARRA ROAD 91364
- Application / Permit
- 23016-10000-19740
- Plan Check / Job No.
- B23LA11039
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- REPAIR BUILDING ROOF STRUCTURE AFTER TREE DAMAGE PER ENGINEERS CALCS IN MULHOLLAND SPECIFIC PLAN
- Permit Issued
- Issued on 6/6/2024
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 2/25/2025
Permit Application Status History
| Submitted | 6/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2023 | ZAW HAN |
| Corrections Issued | 6/27/2023 | ZAW HAN |
| Building Plans Picked Up | 6/28/2023 | APPLICANT |
| Applicant returned to address corrections | 11/13/2023 | WEIJIAN HUANG |
| Plan Check Approved | 6/5/2024 | DANIEL SANJUAN |
| Issued | 6/6/2024 | APPLICANT |
| Permit Finaled | 2/24/2025 | JOHN HAYES |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 2/5/2024 | CARLOS AGUILERA |
| Tenant Habitability Plan | Cleared | 2/5/2024 | RICARDO BOHORQUEZ |
| Miscellaneous | Cleared | 2/15/2024 | RUBEN VASQUEZ |
| Specific Plan | Cleared | 5/29/2024 | JUDE HERNANDEZ |
Contact Information
| Contractor | Marathon Enterprises Inc; Lic. No.: 1077748-B | 1050 W ALAMEDA AVE #306 BURBANK, CA 91506 |
| Engineer | Morales,, Ricky Augusto; Lic. No.: C40289 | 550 DEEP VALLEY DR STE 273 PALOS VERDES ENGINEERING CORP. ROLLING HILLS ESTATES, CA 90274 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 7/1/2024 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 7/1/2024 | Corrections Issued | HENRY KIM |
| Deputy Drilled-In Anchors | 7/2/2024 | Conditional Approval | HENRY KIM |
| BUILDING-Rough-Frame | 7/17/2024 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 7/17/2024 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2024 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 7/17/2024 | Corrections Issued | HENRY KIM |
| Insulation | 8/13/2024 | No Access for Inspection | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2024 | Corrections Issued | HENRY KIM |
| Insulation | 9/16/2024 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 9/16/2024 | Not Ready for Inspection | JOHN HAYES |
| Special/Order Compliance | 9/16/2024 | Corrections Issued | JOHN HAYES |
| BUILDING-Rough-Frame | 9/17/2024 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2024 | Approved | HENRY KIM |
| Footing/Foundation/Slab | 9/17/2024 | Approved | HENRY KIM |
| Green Building Rough | 9/17/2024 | Approved | HENRY KIM |
| HVAC-Rough | 9/17/2024 | Corrections Issued | HENRY KIM |
| Insulation | 9/17/2024 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 9/17/2024 | Corrections Issued | HENRY KIM |
| HVAC-Rough | 10/24/2024 | Partial Approval | JOHN HAYES |
| Interior/Exterior Lathing | 10/24/2024 | Corrections Issued | JOHN HAYES |
| HVAC-Rough | 11/18/2024 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 11/18/2024 | Corrections Issued | HENRY KIM |
| Interior/Exterior Lathing | 12/27/2024 | Approved | JOHN HAYES |
| Drywall Nailing | 1/2/2025 | Approved | CHRIS CHRISTENSEN |
| Final | 2/24/2025 | Permit Finaled | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/24/2025 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 2/24/2025 | Approved | JOHN HAYES |