8529 W KYLE ST 91040

Certificate Information: 8529 W KYLE ST 91040

Application / Permit
23016-10000-19722
Plan Check / Job No.
B23LA11033
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) ONE STORY DETACHED STORAGE INTO ADU PER WFPP (Conversion of Accessory Building per State Law, CA Govt. Code 65852.2(e)(1)(A))
Permit Issued
Issued on 8/25/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2023 APPLICANT
Assigned to Plan Check Engineer 6/14/2023 JOSEPH RAFOLS
Corrections Issued 6/14/2023 JOSEPH RAFOLS
Plan Check Approved 7/20/2023 AUNG SOE
Issued 8/25/2023 APPLICANT
CofO in Progress 2/14/2024 WILLIAM WREN
Permit Finaled 3/2/2024 RUBEN SALAS
CofO Issued 3/2/2024 RUBEN SALAS
Permit Finaled 3/2/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/15/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 6/15/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/21/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/11/2023 Partial Inspection WILLIAM WREN
Deputy Drilled-In Anchors 9/15/2023 Conditional Approval DAVID MATSON
Sewer 9/15/2023 Approved WILLIAM WREN
Underground Mechanical 9/15/2023 Partial Approval WILLIAM WREN
Footing/Foundation/Slab 9/26/2023 Approved WILLIAM WREN
PLUMBING-Rough 9/26/2023 Partial Approval WILLIAM WREN
BUILDING-Rough-Frame 10/10/2023 Approved WILLIAM WREN
ELECTRICAL-Rough 10/10/2023 Corrections Issued WILLIAM WREN
PLUMBING-Rough 10/10/2023 Approved WILLIAM WREN
ELECTRICAL-Rough 10/17/2023 Approved WILLIAM WREN
Insulation 10/17/2023 Corrections Issued WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 10/27/2023 Partial Approval WILLIAM WREN
Insulation 10/27/2023 Conditional Approval WILLIAM WREN
Shower Pan 11/7/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 11/14/2023 Order to Comply Issued JUAN VALENZUELA
Drywall Nailing 11/29/2023 Approved JUAN VALENZUELA
Insulation 11/29/2023 Approved JUAN VALENZUELA
Green Building Rough 12/5/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 12/5/2023 Approved WILLIAM WREN
Final 1/16/2024 Corrections Issued WILLIAM WREN
Green Building Final 1/16/2024 Not Ready for Inspection WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 1/16/2024 SGSOV Approved WILLIAM WREN
Smoke Detectors 1/16/2024 Approved WILLIAM WREN
Final 1/30/2024 Corrections Issued CRAIG DAVIS
Green Building Final 1/30/2024 Approved CRAIG DAVIS
Final 2/2/2024 Not Ready for Inspection MATTHEW NELSON
Final 2/6/2024 OK to Issue CofO WILLIAM WREN