1119 1/2 S KENISTON AVE 90019

Certificate Information: 1119 1/2 S KENISTON AVE 90019

Application / Permit
23016-10000-19684
Plan Check / Job No.
B23LA11029
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO (N) DETACHED ADU PER CA Govt. Code 65852.2(e)(1)(A). "COMPLY WITH DEPARTMENT ORDER effective date 03/29/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 6/28/2024
Issuing Office
Metro
Current Status
Issued on 6/28/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/14/2023 APPLICANT
Assigned to Plan Check Engineer 6/23/2023 VICTOR CHEN
Corrections Issued 6/24/2023 VICTOR CHEN
Building Plans Picked Up 6/29/2023 APPLICANT
Plan Check Approved 5/16/2024 FERNANDO FLORES
Issued 6/28/2024 APPLICANT

Permit Application Clearance Information

Tenant Habitability Plan Cleared 12/11/2023 RICARDO BOHORQUEZ
Construction near power lines Cleared 4/11/2024 RIDWAN HARDY
Address approval Cleared 5/14/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 5/14/2024 CHRISTINA BRACO
Sewer availability Cleared 5/14/2024 CHRISTINA BRACO

Contact Information

Contractor Glenford Construction; Lic. No.: 950038-B 1436 7TH STREET #U      RIVERSIDE, CA 92507

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 9/11/2024 Not Ready for Inspection WILLIAM MICHALAK
ELECTRICAL-Rough 9/11/2024 Partial Approval WILLIAM MICHALAK
Green Building Rough 9/11/2024 Not Ready for Inspection WILLIAM MICHALAK
METHANE-Rough 9/11/2024 Approved WILLIAM MICHALAK
PLUMBING-Rough 9/11/2024 Partial Approval WILLIAM MICHALAK
Deputy Drilled-In Anchors 9/26/2024 No Access for Inspection WILLIAM MICHALAK
BUILDING-Rough-Frame 10/2/2024 Corrections Issued WILLIAM MICHALAK
Green Building Rough 10/2/2024 Not Ready for Inspection WILLIAM MICHALAK
BUILDING-Rough-Frame 10/8/2024 Partial Approval WILLIAM MICHALAK
Green Building Rough 10/8/2024 Not Ready for Inspection WILLIAM MICHALAK
Insulation 10/22/2024 Approved WILLIAM MICHALAK
Interior/Exterior Lathing 10/22/2024 Corrections Issued WILLIAM MICHALAK
Drywall Nailing 10/30/2024 Approved LUIS CORRAL
Interior/Exterior Lathing 10/30/2024 Approved LUIS CORRAL
BUILDING-Rough-Frame 1/7/2025 Approved LUIS CORRAL
Final 1/7/2025 Corrections Issued LUIS CORRAL
Green Building Final 1/7/2025 Approved LUIS CORRAL
Green Building Rough 1/7/2025 Approved LUIS CORRAL
SGSOV-Seismic Gas S/O Valve 1/7/2025 SGSOV Not Ready LUIS CORRAL
Smoke Detectors 1/7/2025 Corrections Issued LUIS CORRAL